On November 11, Shanghai Yiyun 60MW/240MWh grid-side independent energy storage power station project started.
It is reported that the project is located in Fengxian District Comprehensive Bonded Zone, Shanghai, with a total investment of 270 million yuan , covering an area of about 26.5 mu, and is constructed by Shanghai Yiyun Intelligent Energy Co., Ltd.

The project plans to build a 60 MW/240 MWh new electrochemical energy storage power station. It includes 28 sets of 1.25 MW/5MWh lithium iron phosphate energy storage DC cabins, 20 sets of 1.25 MW/5MWh semi-solid energy storage DC cabins, 12 sets of step-up integrated transformers, 1 110kV step-up station and corresponding living and office prefabricated cabins. Lithium iron phosphate battery energy storage system (35 MW/140MWh) and new semi-solid battery energy storage system (25 MW/100M Wh) are proposed to be used in the
project. In addition, the project plans to build a new 110kV booster station, which will be connected to 110kV Putianjing Station with a 110kV line.