1.23 GW PV Modules Delivered Fast! How did GCL Integration do it?

2025-09-28 17:45:55

Over the vast Gobi, delivery vehicles, like steel dragons, meander hundreds of miles through the scorching sun and dust-this is the shocking scene of Xiexin Integration successfully completing the delivery of 1.23 GW photovoltaic modules from Shenneng Xinjiang Hefeng.

On the

vast Gobi, delivery vehicles are like steel dragons winding hundreds of miles. Traveling through the scorching sun and sand and dust-this is precisely the successful completion of the 1.23 GW of Shenneng Xinjiang Hefeng" by GCL Integration. Xiexin Integration realizes one-stop closed-loop of component R & D, production, transportation and delivery with efficient collaboration of the whole chain. It not only highlights the integration of GCL in

components are delivered in

60 days to set a new benchmark

for high efficiency in the industry. Facing the challenges of tight schedule and heavy tasks of Xinjiang Hefeng Project, Xiexin Integration shows strong execution and efficient collaboration ability, Xiexin Integration starts the " extreme response mode ", sets up a cross-departmental special team to tackle key problems, compresses the component delivery cycle through innovative means such as digital production scheduling and intelligent logistics collaboration, and efficiently completes from order confirmation to component delivery. Zero delay in the whole transportation, successfully completed in only 60 days.

"This is not only a breakthrough in speed, but also a comprehensive test of system capability.". The head of Xiexin Integrated Components Business Department said that the project team realized the customized production and precise distribution of N-type TOPCon high-efficiency components through the three-dimensional linkage of " R & D-production-logistics " to ensure that each component meets the strict standards of the northwest cold, strong wind and sand environment.

The NT12 independently developed by GCL is used in this project R/66GDF component , which has the ability to adapt to the whole scene: whether it is the decentralized layout of industrial and commercial roofs or the large-scale laying of centralized power stations; Whether it is a vast Gobi or a desert full of yellow sand, its excellent load resistance, sand resistance and corrosion resistance can easily cope with the complex global terrain, showing strong environmental adaptability and stability. It has been verified in a number of " photovoltaic + sand control" projects around the world: domestic support for the application of Ningxia, Xinjiang, Inner Mongolia and other projects to promote the transformation from "sand advancing and people retreating" to "green advancing and sand retreating"; At the same time, in overseas and other regions, we will help achieve a win-win situation of clean energy substitution and ecological restoration, and provide a replicable "China Plan" for global energy transformation and sustainable development.

In order to deeply verify the reliability of components under extreme temperature changes, GCL Integration follows the IEC 61215-2: 2021standard. In the extreme temperature environment of-40 ℃ to 85 ℃, in order to further verify the extreme performance of components, GCL Integration has tightened the test conditions. The number of thermal cycle tests was further increased to 600 . The results show that GCL integrated components show excellent temperature resistance, can easily withstand extreme temperature changes, and the power attenuation is controlled within 2%, which is far better than IEC standard requirements, demonstrating its strong performance stability.

Shenneng Xinjiang's 2 million kilowatt photovoltaic project is located in Hefeng, Tacheng Prefecture and Bukesaier Mongolian Autonomous County, Xinjiang Uygur Autonomous Region. In the industrial park, as a key project of Xinjiang's "14th Five-Year Plan" new energy planning, after completion, the equivalent full-load utilization hours of the power station in the first year are 1519.65 hours, and the average equivalent full-load utilization hours of the power station in 25 years are 1445.97 hours, which can provide 3.259 billion kilowatt-hours of clean electricity for the power grid every year, and save 1.304 million tons of standard coal every year. Accordingly, sulfur dioxide emissions can be reduced by about 97800 tons, nitrogen oxides by about 48900 tons, carbon dioxide (CO2 ) by about 3.25 million tons and carbon dust by about 88

tons per year. It provides an economic and feasible solution for the "photovoltaic + sand control" model in Northwest China.

"Every component is a demonstration of our commitment to carbon neutrality.". "Xiexin Integrated Sales Director said that in the future, it will continue to use" Xiexin Speed "to enable global energy transformation, so that green power can illuminate more sustainable development paths.

All can be viewed after purchase
Correlation

Over the vast Gobi, delivery vehicles, like steel dragons, meander hundreds of miles through the scorching sun and dust-this is the shocking scene of Xiexin Integration successfully completing the delivery of 1.23 GW photovoltaic modules from Shenneng Xinjiang Hefeng.

2025-09-28 17:45:55

Zhejiang Aikang plans to invest in the construction of HJT perovskite tandem battery research and production base project in Hangzhou Qianjiang Economic Development Zone in the future, with a total investment of about 1 billion yuan.

2023-12-30 23:07:59

The project will invest in the construction of 3GW perovskite photovoltaic modules and 1200 tons of perovskite materials per year, and simultaneously plan project of 30GW perovskite modules, the project of 10000 tons of perovskite materials per year and the project of perovskite module equipment. At the same time, the project will rely on Fuyang Institute of Advanced Studies to set up a perovskite battery research Institute.

2023-12-30 23:04:35

The first large-scale distributed photovoltaic project in Songyuan City, Jilin Province

2023-11-28 15:47:06

TBEA Zhundong 200,000 tons of high-end electronic grade polysilicon green low-carbon circular economy phase I 100,000 tons project has been completed, and is currently in the process of reaching quality and production.

2023-11-16 17:07:55

Hongjun New Heterojunction Solar Cell and Module Production Base held the preliminary delivery of the plant and the entry ceremony of the production equipment.

2023-11-16 11:23:47

The base is planned to have two fully automated production lines, with an annual production capacity of 1.8GW and an output value of 3 billion yuan.

2023-11-10 10:35:12

Will supply Mattel Battery Factory.

2023-11-10 09:19:35

On March 10 this year, Zhengqi Holdings and Ma'anshan Municipal Government signed a contract for the industrialization project of intelligent manufacturing of 20g W high-efficiency N-type batteries.

2023-11-07 09:52:30

The total investment of Guosheng Heterojunction 10g W Double Carbon Industrial Park Project is planned to be 5.2 billion yuan.

2023-11-07 09:30:52

The total investment of the project is more than 6.8 billion yuan, and 30 N-type high-efficiency battery production lines have been built.

2023-11-06 09:25:30

Mubang Hi-Tech, Yidao New Energy and Xinzhou Economic Development Zone Management Committee jointly signed an investment agreement for the project of pulling 20GW N-type monocrystalline silicon rods annually.

2023-11-02 10:07:29

Liansheng Science and Technology Nantong 12 GW Heterojunction Battery Project will start construction this year, with a total investment of 7 billion yuan, and the project will be divided into three phases.

2023-10-30 10:15:30

On October 27, less than a month after the first phase of monocrystalline silicon project in Sany Shuozhou was put into operation, Sany Group successfully cooperated with Pinglu District, Shuozhou City, Shanxi Province, to increase the integrated layout of the whole photovoltaic industry chain.

2023-10-30 10:12:49

Successfully signed the cooperation agreement between Sanyi Shuozhou Phase II Large-size Ultra-thin Monocrystalline Silicon Wafer Project and Sanyi Group Pinglu District Distributed Photovoltaic Power Generation Project.

2023-10-27 17:21:07

The company's secretary said that the first GW production line of the company's photovoltaic cell project has been successfully trial-produced and has the conditions for production.

2023-10-26 09:55:48

The project will be listed for sale in the near future and will start construction within next year.

2023-10-24 10:22:58

On the evening of October 22, Yisheng Science and Technology announced that it planned to invest in the construction of "New Energy 12 GW Heterojunction Battery Project" with an investment of 2 billion yuan in the first phase.

2023-10-23 10:59:56

At 11:58 on September 18, the first TOPCon high-efficiency battery of Bangjie New Energy Yangzhou Base Phase I was successfully launched, which means that Bangjie has taken an important step in transforming the new energy industry.

2023-09-25 15:03:00

As a major project, Zhongqing Advanced Battery Manufacturing (Chizhou) Co., Ltd. participated in the signing of a centralized contract at the opening ceremony with an annual output of 12 GW high-efficiency TOPCON photovoltaic cell project (with an investment of 1.2 billion yuan in the first phase).

2023-09-21 11:47:47

The project was formally signed and settled on February 23 this year, and construction began on March 15. From the signing of the contract to the construction and then to the full production, the project has achieved 150 days of first-line production and 180 days of full production.

2023-09-21 11:41:38

Liansu Group will continue to expand 1.2G W PV module production line in Indonesia, featuring new energy materials, new energy equipment and new energy applications, to form an international PV module production center with a scale of about 2.4G W.

2023-09-20 11:04:22

After the completion of the second phase of the project, it will have the production capacity of 10g W crystalline silicon solar slices and 10g W batteries every year.

2023-09-20 10:52:19

On September 4, the first monocrystalline furnace of Shuangliang Phase III 50GW monocrystalline silicon project was successfully installed, marking that the main production equipment of Phase III project formally entered the installation stage, laying a solid foundation for the early commissioning of Phase III project.

2023-09-11 11:12:03

The highest power module in the mass production heterojunction module reaches 720 W.

2023-09-06 13:12:16

Recently, yuanda Residential Workers announced that Changsha yuanda Residential Industry Group Co., Ltd. decided to apply for bankruptcy reorganization on its own. Recently, the company is facing a serious debt and business crisis, although it has taken a number of self-help measures, but the effect is not obvious. According to the relevant laws and regulations, the company meets the conditions of bankruptcy reorganization, and has the advantages of reorganization value and platform resources.