On November 11, the Shuangbai Branch of the Bureau of Ecology and Environment of Chuxiong Prefecture, Yunnan Province, issued a public announcement on the proposed review of the environmental impact assessment documents of Bangsan Photovoltaic Power Generation Project .
The announcement shows that the project is located in Fa Town, Shuangbai County, and the construction unit is Datang (Shuangbai) New Energy Co., Ltd., with a total area of 84.21 hm2 and a rated capacity of 60 MW. The installed capacity of battery modules is 70.6888 MW , and the capacity ratio is 1.25.
The project has a total of 22 PV arrays and 3884 strings. It is planned to install 108,752 PV modules and configure 200 inverters. There are 22 box-type transformers, which collect power with two collecting lines. The collecting lines are directly buried and overhead. The length of directly buried cables is 8.6 km, and the length of overhead lines is 8.321 km.