Digital New Energy DataBM. Com has learned that on June 25, the EIA of two photovoltaic power plant projects under Datang Group and China Resources Group has made new progress.
Datang Hanbin Stone Staircase 100MW Composite Photovoltaic Power Generation Project
on June 25. The People's Government of Hanbin District, Ankang City, Shaanxi Province issued a public announcement on the approval decision of the environmental impact assessment document of Datang Hanbin Shiti 100000 kilowatt composite photovoltaic power generation project (major changes).
Datang Hanbin Shiti 100000 kilowatt composite photovoltaic power generation project is located in Shiti Town and Guanjia Town , Hanbin District, Ankang City, Shaanxi Province, with a total investment of 50 million yuan . A photovoltaic field with a total scale of 100,000 kilowatts will be built, and a 110 kV booster station and a 5.2 km outgoing line will be built.
According to the publicity content, the project is a major change re-approval project . The main changes are as follows: the construction area of the photovoltaic array has changed, the overall layout of the photovoltaic area of the project has changed, and the area of the photovoltaic array area has increased . The capacity of PV modules , the number of PV modules, the number of inverters, the construction contents of 35kV box-type transformers, 35kV collector lines and roads have all changed; After the adjustment, the land use is more dispersed and new environmentally sensitive targets are added. This assessment only includes the environmental impact assessment of photovoltaic field project, booster station and transmission line to implement the original environmental impact assessment content. The construction of the
photovoltaic area in Shiti Town has been completed in accordance with the requirements of the original EIA, and the construction of the new photovoltaic area in Guanjia Town has not started.
China Resources Yunnan 50MW Photovoltaic Power Generation Project
On the same day, the People's Government of Xishuangbanna Dai Autonomous Prefecture of Yunnan Province issued a notice to review the EIA documents of Manso Photovoltaic Power Generation Project.
It is reported that the project is located in Menglong Town, Jinghong City, Xishuangbanna Prefecture, Yunnan Province, and is constructed by Huarun New Energy (Jinghong) Co., Ltd., a holding subsidiary of Huarun Electric Power New Energy Investment Co., Ltd., with a total investment of 200 million yuan, a planned rated installed capacity of 50 MW, and 96,712 615 Wp double-sided components. The floor area is 87.84h ㎡, and the construction mode is complementary of medicine and light.