Located in Dewo, Yilong New District, the third phase project of Dongfenglin Avenue, the Redundant Sang Bridge, has been progressing smoothly since its construction. At present, it has entered the concrete pouring stage of the main arch bridge. The project is expected to be completed and put into operation early next year.
Project manager Ou Wenming introduced that at present, the first pouring of concrete on the left side will strive for the second pouring at the end of May. After the completion of the pouring, the steel bar binding and concrete pouring on the right side will be put into operation immediately; It is expected that the first concrete will be poured on the right side at the end of May and the second concrete will be poured at the beginning of June. After the successful completion of the two main arch bridges, more than 60% of the project tasks of the contract section of Dongfenglin Avenue will be basically completed. In order to complete the project and put it into use as soon as possible, the owner, the construction party and the supervisor work together to overcome difficulties and complete various construction tasks at the prescribed time.
It is understood that the Redundant Sang Bridge of Dongfenglin Avenue Phase III Project is 168 meters long, with a contract period of one year. It connects Muza in the north and Dewo in the south, and is an important traffic artery connecting the two places. After the completion of the project, the road traffic hub along the line will be further improved, which will not only facilitate people's travel, but also play a positive role in promoting the economic development of the area along the line.