Digital New Energy DataBM. Com learned that on April 21, the Xizang Xizang Southeast Clean Energy Development Co., Ltd. issued a tender announcement for research and survey and design of three new energy projects with a total scale of 14.04 GW. It includes 13.2G W photovoltaic projects and 0.84 GW wind power projects.

(Southeast Xizang Company) Changdu Basu County Lalong 4 million kilowatt photovoltaic project
According to the announcement, the construction scale of Changdu Basu County Lalong 4 million kilowatt photovoltaic project is 4000MW , located in Basu County and Zuogong County of Changdu City. The term of
project survey and design service is from the effective date of the contract to the date when all the 4 million kilowatt photovoltaic projects have passed the completion acceptance. ( It is tentatively scheduled from June 1, 2026 to May 31 , 2031, 1825 calendar days, and the specific start time of survey and design services shall be subject to the written notice of the Tenderee). The bidding scope of the
project is the survey and design in the feasibility study stage (reaching the depth of preliminary design), the survey and design in the construction drawing design stage, the preparation of as-built drawings and technical services. Survey and design services for the whole process from the project feasibility study to the completion of the whole project.
(Southeast Xizang Company) The tender announcement of Xingong 5.5 million kilowatt photovoltaic and Randuo 290000 kilowatt wind power project
in Basu County, Changdu shows that the construction scale of Xingong 5.5 million kilowatt photovoltaic and Randuo 290000 kilowatt wind power project totals 5790 MW. The photovoltaic project of 5,500MW and the wind power project of 290MW are located in Basu County and Zuogong County of Changdu City. The term of
project survey and design service is from the effective date of the contract to the date when the survey designer completes all the contract work and submits all the survey and design results. ( Tentatively from June 1, 2026 to May 31 , 2029, 1095 calendar days, and the specific start time of survey and design services shall be subject to the written notice of the Tenderee). The bidding scope of the
project is the survey and design in the feasibility study stage, the survey and design in the preliminary design stage and the technical services. Including but not limited to the overall (or phased) construction planning of wind farms (including booster stations) and photovoltaic stations, review of wind and solar resources, topographic mapping, micro-site selection, etc.
(Southeast Xizang Company) The tender announcement of Lajiao 3.7 million kilowatt photovoltaic and 850000 kilowatt wind power projects
in Basu County, Changdu, shows that the construction scale of Lajiao 3.7 million kilowatt photovoltaic and 850000 kilowatt wind power projects totals 4250MW. It includes a photovoltaic project of 3700MW and a wind power project of 550MW. The construction site is located in Basu County, Changdu City. The term of
project survey and design services is from the effective date of the contract to the date when the 3.7 million kilowatt photovoltaic + 550,000 kilowatt wind power project has passed the completion acceptance. ( It is tentatively scheduled from June 1, 2026 to May 31 , 2031, 1825 calendar days, and the specific start time of survey and design services shall be subject to the written notice of the Tenderee). The bidding scope of the
project includes the survey and design in the feasibility study stage, the survey and design in the preliminary design stage, the survey and design in the construction drawing design stage, the preparation of as-built drawings and technical services. Survey and design services for the whole process from the project feasibility study to the completion of the whole project.