Announcement of Yingde Runfeng New Material Science and Technology Co., Ltd. before the Planning Approval of the Relocation Project of Cement Grinding Station with Annual Output of 1 Million Tons

2023-11-08 10:03:11

The total planned land area of the project is 18886 26 square meters, the building density is 44.20%, the plot ratio is 1.04, and the green space ratio is 15.09%.

Yingde Runfeng New Material Technology Co., Ltd. has applied to the Management Committee of Yingde High-tech Zone for the construction of the relocation project of the cement grinding station with an annual output of 1 million tons. The construction location and specific indicators of the project are shown in the attached figure. After reviewing the relevant information by the Management Committee of Qingyuan Yingde High-tech Industrial Development Zone, and in accordance with the provisions of the Law of the People's Republic of China on Urban and Rural Planning and the Measures for Publicizing the Planning of Qingyuan Urban and Rural Planning Bureau, it is decided that from November 8, 2023 to November 17, 2023, the relevant matters of the proposed construction project will be publicized on the spot to solicit the opinions of the surrounding residents.

Project overview: The total planned land area of the project is 1,888.6.26 square meters, the building density is 44.20%, the plot ratio is 1.04, and the green space ratio is 15.09%. The proposed project covers an area of 4021.01 square meters, involving six buildings, including mixed material storage shed, clinker storage, cement mill, cement bulk storage, cement packaging room, power distribution room, as well as admixture storage, cement storage, wastewater collection pool, rec irculating pool, waste oil collection room and other structures. The total building area is 5153.48 square meters and the capacity area is 7535.82 square meters.

Address:

Yingde Hongxing Industrial Park Zone

3 Tel: 0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-0763-064 2630331

If you have any comments Written representations or written suggestions may be submitted to the Management Committee of Qingyuan Yingde High-tech Industrial Development Zone within 10 days from the date of publication. Those who fail to submit within the time limit shall be deemed to have waived the above rights, and the Management Committee of Qingyuan Yingde High-tech Industrial Development Zone shall go through the relevant formalities in accordance with the relevant procedures.


All can be viewed after purchase
Correlation

Zaozhuang Huyuan Industrial Co., Ltd. plans to build a φ4.2 × 13m cement mill with an annual capacity of 1.1 million tons. According to the Notice on Printing and Issuing Several Measures for Resolutely Curbing the Blind Development of "Two High" Projects (Lu Zheng Ban Zi [2021] No.98) and the Implementation Measures for Replacement of Cement Grinding Capacity in Shandong Province (Lu Gong Xin yuan [2022] No.53), the enterprise has formulated a capacity replacement plan, which is now publicized and the public is welcome to supervise.

2024-09-12 16:42:06

The total planned land area of the project is 18886 26 square meters, the building density is 44.20%, the plot ratio is 1.04, and the green space ratio is 15.09%.

2023-11-08 10:03:11

On September 26, Guizhou issued a peak-staggering production plan for the fourth quarter, requiring that all new dry-process cement clinker production lines in the province be shut down for 65 days + N in the fourth quarter, that is, no less than 65 days per line. The original text of off-peak production is as follows: