DBM Weekly Review: Bidding Scale Drops by 86%! Abandoned Bid, Delayed Frequent, "Silver Ten" Collection Market can Hold up?

2025-10-20 09:18:49

After the National Day, a small number of collection projects were released, large-scale projects were scarce, and "Silver Ten" was slightly deserted.

After the

National Day, a small number of collection projects were released, large-scale projects were scarce, "Silver Ten" was more than half, the market was still cold.

According to the incomplete statistics of the digital new energy DataBM. Com, In two weeks (10.1-10.17), the capacity of the announced photovoltaic module collection and calibration and the shortlisted projects is about 0.66 GW . The total amount of bidding projects for centralized procurement of PV modules is about 2.4G W . Among the projects that

have won the bid and the candidates for winning the bid, the bidding unit price of the enterprise is 0.71-0.74 yuan/W , and the average bidding unit price is 0.721 yuan/W (including tax and excluding transportation price). The average price has remained above 0.70 yuan for two consecutive months. The lowest price comes from the project of selecting photovoltaic module suppliers from 2025 to 2026. Shaanxi Hualongxing Digital Energy Technology Co., Ltd. quoted a unit price of 0.715 yuan/W ; The highest price came from the first batch of centralized procurement projects of photovoltaic modules of Yunnan Green Energy New Energy Development Co., Ltd., and Tongwei shares reported a unit price of 0.733 yuan/W .

The specific bidding information is as follows:

the demand for centralized procurement bidding has increased, and the biweekly demand has reached more than 2.4G W. The main procurement types are TOPCon and BC components , and the power requirements are generally above 630W. Up to now, the overall demand for bidding in October is weak, lacking the pull of large-scale centralized procurement projects, and the demand for bidding in the first two weeks has dropped by about 86.1% compared with the same period in September. However, the overall bidding scale increased by 34.7% compared with the same period in 2024.

It is worth noting that, according to the incomplete statistics of the digital new energy DataBM. Com, after the festival, a number of projects issued abandoned bids and delayed announcements, totaling about 95.7 MW . Most of the reasons are that there are less than three qualified bidders. At the same time, the large-scale procurement projects of some state-owned enterprises (37 GW in total) were not announced as scheduled .

At present, in the period of electricity market policy adjustment, the uncertainty of return on investment is increasing. Some bidding units choose to postpone or suspend project bidding to observe the policy landing and market feedback, but at the same time, it indirectly leads to the lack of market confidence. Some investors also say that demand improvement will wait until the first quarter of 2026.

The specific bidding items are as follows:

All can be viewed after purchase
Correlation

After the National Day, a small number of collection projects were released, large-scale projects were scarce, and "Silver Ten" was slightly deserted.

2025-10-20 09:18:49

This week, the price sentiment of photovoltaic module market is still strong, but the actual transaction market is significantly differentiated.

2025-09-26 16:21:47

The centralized market demand is obviously warmer than that from Q2 to the beginning of Q3.

2025-09-20 15:01:46

The upstream and downstream game of the photovoltaic industry chain is more significant, and the price of silicon materials is supported and pushed up by the policy, but the component side has been partially loosened and declined.

2025-09-19 14:55:24

At present, the supply of 182/183 and 210 square cells on the market is tight, and some downstream component manufacturers have been affected by the shortage.

2025-09-10 17:55:58

In the past two weeks, the procurement demand for components of centralized photovoltaic power plant projects has been temporarily quiet, the release of bidding projects is less, and the demand for centralized procurement in September is not clear.

2025-09-06 16:35:28

This week, the PV module market is in an observation period, with Atlas and Xiexin Integration raising prices slightly, but a large number of low-cost modules are appearing in the downstream market.

2025-09-05 15:33:50

According to the incomplete statistics of digital new energy DataBM. Com, the component production schedule in September is expected to be around 46-50GW. Although some component products are "out of stock" and "waiting for goods", manufacturers are not willing to increase production.

2025-08-29 15:17:44

This week, China Resources Power 3GW and Huadian Group 20GW PV module collection project was opened.

2025-08-23 12:12:08

The procurement demand for centralized photovoltaic project components has risen sharply, the bidding demand has exceeded 20GW, and the "five big and six small" procurement is being released.

2025-08-11 09:10:42

In the past two weeks, the procurement demand for centralized photovoltaic project components has been quiet again, but a large number of pre-centralized projects have been settled. According to the incomplete statistics of the Digital New Energy DataBM. Com, the capacity of the announced photovoltaic module bidding and shortlisted projects in two weeks (7.12-7.25) was about 1.94 GW, and the total amount of photovoltaic module bidding projects was about 0.29 GW.

2025-07-28 09:07:59

According to the survey of Digital New Energy DataBM. Com, seven of the top 10 enterprises have raised their component quotations. In the first half of the week, Longji Green Energy and Dongfang Risheng followed up and raised their quotations by 0.02-0.03 yuan/W. Some second-and third-tier manufacturers were slightly affected by the rising cost of raw materials. However, the transaction of new price orders is extremely limited, and the characteristics of "price without market" are significant.

2025-07-24 09:00:19

In the first half of the week, the actual price increase action of photovoltaic module manufacturers was limited, and the bargaining space was still significant, showing the characteristics of "strategic price increase".

2025-07-16 17:42:29

In the past two weeks, the procurement demand for centralized photovoltaic project components has increased significantly, and the demand for centralized procurement of state-owned enterprises is slowly releasing.

2025-07-14 09:06:30

According to the survey of Digital New Energy DataBM. Com, the price of photovoltaic modules fluctuated greatly in the first half of 2025 due to market competition and policy changes.

2025-07-07 10:58:40

This week, the market for photovoltaic modules declined steadily, with two leading manufacturers following up on price cuts, and three small manufacturers all cutting prices. According to the incomplete statistics of digital new energy DataBM. Com, the domestic photovoltaic module production schedule was slightly reduced in July, and the head manufacturer's production schedule was divided.

2025-06-27 14:55:42

According to the incomplete statistics of the Digital New Energy DataBM. Com, the capacity of the photovoltaic module centralized procurement bidding and shortlisted projects that have been publicized in two weeks (6.7-6.20) is about 0.61 GW, and the total amount of photovoltaic module centralized procurement bidding projects is about 1.09 GW.

2025-06-20 16:06:22

This week, the market price of photovoltaic modules remained stable as a whole. After the SNEC exhibition, the price of PV modules has not been adjusted, and it is expected that there will be a decline of 0.01-0.02 yuan/W in late June.

2025-06-16 09:08:20

In the first week of June, the PV module market continued the downturn of price reduction and production reduction.

2025-06-09 09:08:39

According to the incomplete statistics of the Digital New Energy DataBM. Com, the capacity of the announced photovoltaic module bidding and shortlisted projects in two weeks (5.17-5.30) was about 0.43 GW, and the total amount of photovoltaic module bidding projects was about 3.66 GW.

2025-06-03 09:13:45

The lowest price has dropped to 210 yuan/kg.

2023-03-22 16:38:18

Recent delivery is relatively tight, and orders are executed at a unified price.

2023-02-16 16:05:54

Is the price of silicon still rising?

2023-02-15 14:36:06

The third wave of price increase of silicon materials is coming after the year!

2023-02-08 16:54:48

Recently, the Portuguese Construction Industry Association (AICCOPN) data showed that as of August, the total domestic cement consumption was 2.657 million tons, down 1.6% from the same period last year. Despite the growth of the residential real estate market, cement consumption still showed a downward trend. In the second quarter of 2025, the housing market was active, with the sales volume, total transaction value and housing price index all rising; in the first seven months, the number of building permits issued and the permitted area of the housing sector increased significantly. In August, the cumulative change of new mortgage credit was 37.7% year-on-year. Public works market indicators also showed strong growth, with significant increases in tenders and contract amounts.