Latest developments! The right bank of the main dam of Zhujiazui Reservoir is poured and capped.

2023-01-13 10:25:23

After 26 months of construction, the main dam project of Zhujiazui Reservoir has been completed with an investment of 100 million yuan, and four dam sections on the right bank have been successfully poured and capped.

After 26 months of construction, the main dam project of Zhujiazui Reservoir has been completed with an investment of 100 million yuan, and four dam sections on the right bank have been successfully poured and capped. On the morning of January

10, the reporter saw at the construction site of Zhujiazui Reservoir in the upper reaches of the Baier River that the main base and the middle and lower structures of the dam had been formed, and the four dam sections on the right bank had been capped. At the junction of the No.9 dam section on the right bank and the mountain, the construction workers were cleaning the gravel, and then the excavation machinery piled up the gravel neatly to prepare for the next pouring. Xia Shunping, technical director of construction and management

of Zhujiazui Reservoir Project, said that the right bank of the dam was poured and capped, which marked that the construction of the dam had successfully achieved the schedule target as planned, and the civil construction of the main project had been basically completed.

Zhujiazui Reservoir is the largest rock-fill concrete gravity dam under construction in Shiyan City. The designed maximum dam height is 55 meters and the dam crest elevation is 338.5 meters. Four dam sections are built on the left and right banks respectively. The four dam sections on the left bank have been poured to an average elevation of 330.5 meters. The No.5 dam section in the middle will be poured as a flood discharge channel. Huang Zuozhong, deputy manager of Zhujiazui Reservoir Project in Haochuan,

Hubei Province, said that the total amount of concrete is about 95000 cubic meters, and 91000 cubic meters have been completed, about 95%.

Zhujiazui Reservoir is responsible for regulating and supplying Baierhe Reservoir and improving the water ecological environment in the central urban area. Since the start of construction in November 2020, the main project has completed an investment of 100 million yuan, accounting for about 83% of the total investment, and is expected to reach the water storage conditions by May 1, 2023.

All can be viewed after purchase
Correlation

After 26 months of construction, the main dam project of Zhujiazui Reservoir has been completed with an investment of 100 million yuan, and four dam sections on the right bank have been successfully poured and capped.

2023-01-13 10:25:23

At 10 a.m. on January 7, the first section of the first pier of Shahe Bridge, the control project of Rufang Section of Jiaotang Expressway, was successfully poured, and a breakthrough was made in the construction of the bridge.

2023-01-09 09:43:23

Recently, the concrete pouring of the entrance guide wall of Luqu Tunnel of Xicheng Railway, which was constructed by the Tenth Bureau of China Railway, was completed, marking that the tunnel project in the tender section formally entered the main construction stage, sounding the charge of Xicheng Railway construction.

2023-01-09 09:36:07

Recently, after 14 hours of continuous operation, Guangzhou-Zhanjiang high-speed rail successfully completed the pouring of the last portal pier across the Haichuan Express Line, achieving the goal of important nodes and laying a solid foundation for the next girder erection construction.

2023-01-06 09:51:34

On September 5, Chairman Shao Jun of China Cement Network and his delegation visited Ningde Conch Cement Co., Ltd. and were warmly received by General Manager Hong Xianli and others. The two sides exchanged views on the situation of Fujian cement market.