On September 16, the Bureau of Ecology and Environment of Ankang City, Shaanxi Province, issued a public announcement on the approval of the environmental impact assessment document of the 100000 kilowatt photovoltaic project in Pingli County, Datang Fuping Thermal Power Co., Ltd.
The environmental impact report shows that the construction unit of the project is Datang Fuping Thermal Power Co., Ltd., Sun Company of China Datang Group. The project is located in Guangfo Town and Luohe Town, Pingli County, Ankang City, with a total investment of 420 million yuan. The total floor area is about 151.4173 hm ², including a new 100MW photovoltaic power station, a planting project and an outdoor 110kV booster station. The construction period of the project is 12 months.
The project is a "tea-light complementary" solar photovoltaic power generation project, with an AC side capacity of 100MW and a DC side installed capacity of 112.46 MWp.
Among them, the photovoltaic array covers an area of garden, which is divided into 228 plots and consists of 36 photovoltaic power generation sub-arrays. 650WpN monocrystalline double-sided double-glass module + 320 kW string inverter + fixed support/flexible support are used for installation, and 36 35kV box-type transformers are set for block power generation and centralized grid connection.
浙公网安备33010802003254号