On April 23, the official website of the Bureau of Ecology and Environment of Yongzhou City, Hunan Province, issued a public announcement on the https://www.databm.
of Xiaojia Town (Niutouwan Village and Niuling Village) in Qiyang City. The photovoltaic power generation project in Xiaojia Town (Niutouwan Village and Niuling Village) of Qiyang City has a total investment of 363.99 million yuan , a construction period of 12 months and an installed capacity of 70 MW. The main contents of the project are 110 kV booster station project and photovoltaic area. The construction unit of this
project is Qiyang Yudean New Energy Co., Ltd., the holding subsidiary of Guangdong Electric Power Development Co., Ltd. (securities abbreviation: Guangdong Electric Power A), and the former is the holding subsidiary of Guangdong Energy Group .
The project has been approved by the EIA document issued by Yongzhou Ecological Environment Bureau on August 15, 2023. Up to now, the project has not started construction.
Because some of the original approved plots are too scattered , it increases the difficulty of centralized supervision, and at the same time, too scattered photovoltaic fields and collector lines may affect the grid-connected effect . Therefore, the construction unit has been relocated. After the
relocation, the construction scale of the project will not change . However, the number of blocks, the number of photovoltaic power generation units and the installed capacity of each unit, the battery " of which 169 were originally planned to be installed. 624 545Wp monocrystalline silicon PERCP type double-sided < a href = "https://www.databm.".