On August 6, the Bureau of Ecology and Environment of Nanjing City, Jiangsu Province issued a public announcement on the acceptance of EIA impact assessment documents for 68 MW agricultural photovoltaic complementary power generation project in Ma'an Street, Huaneng Liuhe District.

The announcement shows that the project belongs to the agricultural-photovoltaic complementary photovoltaic power generation project, located in Huangzhao Village, Ma'an Street, Liuhe District, Nanjing City, with a total investment of 450 million yuan, a land area of about 1151 mu and a construction period of 7 months. Construction of 68 MW (80 MWp at DC side) centralized PV power station. The project adopts 625Wp monocrystalline silicon double-glass double-sided photovoltaic module 131154 block.
The project constructs Huaneng (Nanjing Liuhe) New Energy Development Co., Ltd.