On July 29, the Bureau of Ecology and Environment of Hancheng City, Shaanxi Province, issued a public announcement on the approval decision of the environmental impact assessment document of the 100000 kilowatt composite photovoltaic power generation project (major changes) in Hancheng City.
The announcement shows that Guoneng Hancheng 100000 kilowatt composite photovoltaic power generation project (major changes) is located in Zhiyang Town, Hancheng City, with a total investment of 455.107 million yuan and a construction period of 8 months. The land area of the photovoltaic area is 1,930,745 ㎡. The proposed installed capacity of the
project is 100MW, 189,228 635 Wp monocrystalline silicon double-sided PV modules are selected, and the size of PV modules is 2278mm × 1134mm × 30mm. In July
2024, the EIA document of the project was approved by Hancheng Ecological Environment Bureau. However, part of the land of the original evaluation project has not been transferred successfully, resulting in changes in the actual land acquisition process. "After the change, the original land before the change will not continue to be used , and the area after the change is all the new area ." The construction unit of the

project is Guoneng Hancheng New Energy Co., Ltd. The controlling shareholder of the company is Shaanxi Electric Power Co., Ltd. of the State Energy Group.