Shanxi 200 MW PV Module Centralized Procurement Project Bidding Delayed for the Sixth Time!

2026-04-13 09:04:05

In the following two months, six extension announcements were issued successively. According to the latest announcement on April 9, the submission and opening time of project bidding documents was postponed to April 16.

On April 9, Shanxi International Energy Group New Energy Investment Management Co., Ltd. issued another tender extension announcement for the centralized procurement project of photovoltaic modules in 2026. This is the sixth time that the tender for the project has been postponed . On January 28

, 2026, Shanxi International Energy Group New Energy Investment Management Co., Ltd. issued a tender announcement for the centralized procurement project of photovoltaic modules in 2026, with an estimated capacity of 199.6297 MW . Procurement of PV modules for investment or urban construction projects of enterprises affiliated to Shanxi International Energy Group New Energy Investment Management Co., Ltd.

It is mainly used for Gemeng Wuzhai 100MW Linguang Complementary Project (Phase II), Gemeng Lanxian 50MW Photovoltaic Power Generation Project (Phase II), Lanxian " Source-Network-Charge-Storage Integration and Multi-Energy Complementary" Power Generation Project, and Gemeng Shanxi Lanxian High-speed Distributed Photovoltaic Project. ( Shanxi International Energy 2026 Photovoltaic Module Centralized Procurement Project Bidding! )

The purchased module product specification is monocrystalline silicon double-sided double-glass N-type TOPCon photovoltaic module, the module power is 620 Wp, and the cell size is above 182 mm. The delivery cycle is from March to June 2026, and the delivery is carried out in batches. In the

first tender announcement, it is clear that the deadline for submission/opening of tender documents is 09:30 on February 27, 2026.

However, in the following two months, the project has issued six extension announcements. According to the latest announcement on April 9, the submission and opening time of project bidding documents was postponed to April 16 .

All can be viewed after purchase
Correlation

Digital New Energy DataBM. Com learned that on April 2, the Three Gorges Yunneng Power Generation (Huize) Co., Ltd. was fined 103.502 million yuan for "illegal land occupation", and the penalty organ was Huize County Natural Resources Bureau.

2026-04-13 18:06:52

List of Proposed Photovoltaic Power Station Projects Last Week (04.06-04.12)

2026-04-13 18:01:19

Digital New Energy DataBM. Com learned that on April 9, the Bureau of Ecology and Environment of Xishuangbanna, Yunnan Province, issued a public announcement on the environmental impact assessment document of Xinshan Photovoltaic Power Generation Project.

2026-04-13 14:24:27

On April 10, at the 15th China Cement Industry Summit, the Digital New Energy DataBM. Com interviewed He Jingxin, Sales Director of Shanghai Pincheng Jingyao Photovoltaic Technology Co., Ltd. to have in-depth exchanges on market trends, overseas layout and enterprise development.

2026-04-13 14:07:29

On April 13, the Energy Bureau of Honghe Prefecture of Yunnan Province announced the list of 34 new energy project owners selected for the third batch of new energy projects in Yunnan Province in 2025 (the second time).

2026-04-13 11:05:10

Recently, CITIC Bo and Shandong Electric Power Construction Third Engineering Co., Ltd. (Hereinafter referred to as "SEPCOIII") signed the supply agreement of tracking bracket system for PV4 Hazza 1.5G W (AC side) photovoltaic project in Abu Dhabi, United Arab Emirates.

2026-04-13 09:36:54

On April 7, the Qingshuihe Photovoltaic Power Generation Project in Huaping County, Lijiang City, Yunnan Province and the Dapingzi Photovoltaic Power Generation Project in Huaping County, Lijiang City, respectively issued announcements on the competitive selection of public investors, and the tenderer was the Lijiang Development and Reform Commission.

2026-04-13 09:04:24

On April 9, the announcement of EPC general contracting of 100MWp distributed photovoltaic project in Zhangzhou City, Fujian Province was issued.

2026-04-13 09:04:15

In the following two months, six extension announcements were issued successively. According to the latest announcement on April 9, the submission and opening time of project bidding documents was postponed to April 16.

2026-04-13 09:04:05

On April 9, Yunnan Energy Investment announced its investment in the construction of Sejia Photovoltaic Power Generation Project, with a rated capacity of 20 MW (installed capacity of 23.96 MWp) and a total investment of 91.9228 million yuan. The project is located in Malong District, Qujing City, Yunnan Province, with a total construction period of 6 months. The construction unit is Malong Yunnengtou New Energy Development Co., Ltd.

2026-04-13 09:03:55

On April 8, Changxing Huarun Gas Co., Ltd. announced the bidding results of general contracting (EPC) of photovoltaic power generation construction project in 2026.

2026-04-10 18:04:17

A number of policies to promote the construction of photovoltaic and other new energy projects

2026-04-09 17:58:32

On April 7, local time, CGN Laos Northern Clean Energy Base Phase I 1 million kilowatt photovoltaic project (hereinafter referred to as "Laos Phase I Project") was put into operation in Vientiane, Laos, marking the successful operation of the largest single photovoltaic project in Southeast Asia.

2026-04-09 15:46:11

Recently, the commencement ceremony of Xiaozhi 28.5MW Agricultural Photovoltaic Complementary Power Generation Project of Datang Taizhou Company was successfully held in Baoshan Village, Xiaozhi Town, Linhai City, marking that the project has formally entered the stage of comprehensive construction.

2026-04-09 13:35:57

On April 3, the website of Chongqing Municipal People's Government published a list of key projects at the municipal level in 2026, including "four batches" of projects started, under construction, completed and reserved. A total of 1382 projects were started, under construction and completed, with a total investment of about 2.9 trillion yuan.

2026-04-09 11:14:02

On March 11, the People's Government of Honghe Prefecture of Yunnan Province carried out the optimization of 34 new energy projects, including 1564 MW wind power projects and 660 MW photovoltaic projects.

2026-04-09 09:43:27

Specifically in the field of photovoltaic power generation, there are 41 projects with a total installed capacity of more than 6.58 GW.

2026-04-08 16:49:47

According to the EIA documents, the project is located in Qingyang Town, Pingshun County, Changzhi City, Shanxi Province, with a total investment of 400 million yuan and a construction period of 12 months. The 100MW photovoltaic power station is mainly constructed. The main works include civil works such as photovoltaic array equipment foundation, support and fence, as well as supporting works such as photovoltaic modules, inverters, transformers and booster stations.

2026-04-08 14:21:37

Upon the application of Qingtongxia Municipal Development and Reform Bureau, the Shashidun 30 MW photovoltaic power generation project in Qingtongxia Green Power Park was cleared up and abolished due to the abandonment of construction by enterprises.

2026-04-08 10:17:01

On March 30, Zhoucun Branch of the Bureau of Ecology and Environment of Zibo City, Shandong Province, issued a public announcement on the proposed approval of the environmental impact assessment document for the 100 MW photovoltaic power generation project in Wangcun, Zhoucun, Huaneng.

2026-04-07 09:07:43

The third phase of the project, with a total installed capacity of 100,000 kilowatts and an area of more than 2,000 mu, is the first photovoltaic project constructed by Huadian Sichuan Company in the "E + PC" mode.

2026-04-07 09:07:20

According to foreign media reports, on April 2, the French government officially announced plans for the 2026 wind and solar energy auction.

2026-04-07 09:06:52

Since March, 13 photovoltaic projects in Xinjiang, Sichuan and Anhui have been started, with a total scale of 6.3613 GW. Among them, there are two projects above GW level, namely, Huadian Sichuan 1.6GW photovoltaic power generation project and China Nengjian Xinjiang 1.35GW photovoltaic power generation project.

2026-04-07 09:06:30

On March 30, the commencement ceremony of Shanxi Jingneng Tunliu 80MW New Energy Project was held in Heijiakou Village, Tunliu District, Changzhi City.

2026-04-07 09:04:49

On April 2, China Power Investment yuanqu 300 MW Phase II Photovoltaic Composite Project EPC General Contracting Bidding Control Price Change Announcement was issued.

2026-04-07 09:04:38

According to the incomplete statistics of digital new energy DataBM. Com, the capacity of photovoltaic module bidding and shortlisted projects that have been publicized in two weeks (3.21-4.3) is only 0.21 GW, and the total amount of photovoltaic module bidding projects is 8.23 GW.

2026-04-07 09:04:24

On March 27, the Bureau of Ecology and Environment of Wenshan Prefecture, Yunnan Province, decided to approve the environmental impact report form of Ganlongtang Photovoltaic Power Generation Project.

2026-04-07 09:04:12

On April 2, 2026, the government of Kailu County, Tongliao City, Inner Mongolia announced that since the suspension of the filing work, the State Grid Kailu County Power Supply Company has upgraded the county's power infrastructure, and at this stage Kailu County has a certain capacity space for distributed photovoltaic access.

2026-04-03 17:38:05

On April 1, Huaneng Yili Gongliu Industrial Park low-carbon transformation 500000 kilowatt photovoltaic project officially started construction.

2026-04-03 11:16:13

It is reported that China can build Hami "light (heat) storage" 1500 MW base project, with a total investment of about 6.5 billion yuan, formally entered the construction site in May 2024, which is the core project of the second batch of national "Shagehuang" large-scale wind power photovoltaic base construction.

2026-04-03 10:37:46

Digital New Energy DataBM. Com was informed that on March 31, (Chongqing Branch) Datang Chongqing Tongliang District River Water 60 MW and Sanpin 31.36 MW Agricultural Photovoltaic Power Generation New Project EPC General Contracting Successful Candidates were announced.

2026-04-02 17:50:25

On March 26, the official website of the People's Government of Qiannan Buyi and Miao Autonomous Prefecture of Guizhou Province issued the "Announcement of Acceptance of Environmental Impact Report Form for Huazhushan Photovoltaic Power Station Project in Weng'an County".

2026-04-02 17:49:46

On April 1, Huaneng Yili Gongliu Industrial Park low-carbon transformation 500000 kilowatt photovoltaic project officially started construction.

2026-04-02 17:49:23

On March 30, the Development and Reform Commission of Ankang City, Shaanxi Province, issued a public announcement on the proposed abolition of guaranteed photovoltaic power generation projects. Due to the lack of substantive construction, it is proposed to abolish the Hanbin Jianmin 100000 kilowatt agricultural-photovoltaic complementary photovoltaic power generation project.

2026-04-02 10:55:31

The total amount is 1.312 billion yuan, and the lowest unit price is 1.20 yuan/W! Results of Aba Rong'an 1150MW Photovoltaic Project (Phase II) of Dadu River Company | Weekly Project Statistics (3.23-3.29)

2026-04-01 17:51:11

On April 1, Chuxiong Prefecture and Wenshan City of Yunnan Province launched the third batch of market-oriented competitive allocation of new energy projects in 2025, involving a total installed capacity of 2.25447 million kilowatts. Among them, the installed capacity of photovoltaic power generation is 1.035 million kilowatts (1035 MW), and the installed capacity of wind power is 1.2194 million kilowatts. In addition, on March 30, the second batch of new energy projects in Pu'er City in 2025, Ning'er County Xinzhai Phase II Tea-Light Complementary Photovoltaic Project, issued a competitive consultation announcement on the main investors, involving a photovoltaic installed capacity of 140 MW.

2026-04-01 17:26:17

Recently, Gansu Gulang Longdian entered the photovoltaic area of Section I of Zhejiang Huanghuatan 2 million kilowatt photovoltaic project.

2026-04-01 13:45:48

The Digital New Energy DataBM. Com was informed that on March 30, the Ankang Development and Reform Commission of Shaanxi Province issued a public announcement on the proposed abolition of the guaranteed photovoltaic power generation project.

2026-04-01 11:47:41

Digital New Energy DataBM. Com was informed that on March 26, the construction of 100 MW photovoltaic power generation project in Qingtan, Yongchang River, Gansu Province started, and the concrete pouring of the first photovoltaic support foundation pile was successfully completed, laying a s olid foundation for the subsequent support installation, component laying and overall promotion.

2026-04-01 09:01:56

List of Proposed Photovoltaic Power Station Projects Last Week (03.23-03.29)

2026-03-31 18:09:40

From the optimization and upgrading of a production line to the green butterfly change of the whole chain, Yicheng South has created an economic ecosphere of resource recycling through continuous exploration and practice, and has written a new chapter of high-quality development of the cement industry on the development answer sheet. In the future, the enterprise will continue to take the blue sky and white clouds as the volume, the green water and green hills as the pen, and strive to write more brilliant green answers in the construction of beautiful China.

2026-03-31 10:32:14

Digital New Energy DataBM. Com learned that on March 26, Sipaishan Photovoltaic Power Generation Project (Phase II) started smoothly in Bankang Village, Sipaishan Township, Gengma County, Lincang City, Yunnan Province.

2026-03-30 17:33:35

Digital New Energy DataBM. Com was informed that on March 27, the successful candidate for EPC general contracting project of Phase II 100000 kW photovoltaic project in Qinshui County, Jincheng City, Shanxi Province was announced.

2026-03-30 17:33:07

On March 24, the tender announcement for EPC general contracting of Chongqing Huadian Fuling Dishui 60.48 MW Photovoltaic Power Generation Project, a related project of Chongqing Branch of China Huadian Corporation, was issued.

2026-03-30 09:06:38

EIA announcement information shows that the project first obtained the record certificate of Qingxin District Development and Reform Bureau on February 25, 2021, and was approved on April 6, 2022. Construction started in May 2022. Now some photovoltaic areas and booster stations have been completed, and some areas have not been constructed.

2026-03-30 09:06:17

On March 25, the Environmental Protection Bureau of Yangchun City, Guangdong Province, issued a public notice on the review of the environmental impact assessment documents of Yangchun 80 MW Agricultural Hybrid Photovoltaic Power Generation Project of Yangchun Nuclear Run New Energy Co., Ltd.

2026-03-27 18:01:14

Digital New Energy DataBM. Com learned that on March 24, Dongchangfu District Bureau of Liaocheng Eco-environmental Bureau of Shandong Province issued a public announcement on the acceptance of EIA documents for 55 MW photovoltaic power generation project in Zhanglu Town, Datang Binzhou Power Generation Co., Ltd.

2026-03-27 18:00:15

On March 26, the tender announcement for the general contracting (EPC) of the 1 million kilowatt "grass-light complementary" photovoltaic project of Shima Bingdi Integration of the Eighth Division was issued.

2026-03-27 17:58:58

On March 26, the Shaanxi Provincial People's Government issued the "Annual Plan for Key Construction Projects in Shaanxi in 2026".

2026-03-26 17:30:48

It is understood that the company recruited restructuring investors by bidding in 2025, with a starting price of 5.3 million yuan.