16 July, The official website of the Administrative Service Office of the People's Government of Wuqing District, Tianjin, issued the "Wuqing District Administrative Examination and Approval Bureau on Tianjin Xinsheng New Energy Co., Ltd. TBEA Tianjin Wuqing District Sicundian, Announcement of Acceptance of Environmental Impact Report (Form) of Photovoltaic Project in Baigutun Town.

The announcement shows that the project is located in Sicundian Town, Wuqing District, with a total investment of 726 million yuan , a leased area of 4,200 mu, and a total land area of about 4,193 mu. The construction scale is 150MW , 288,112 625W p monocrystalline silicon battery modules are installed , and the construction period is 12 months. The construction unit of the
project is Tianjin Xinsheng New Energy Co., Ltd. Founded in 2021, the company's business scope covers solar power technology, wind power technology services and so on. Equity penetration shows that the company is a subsidiary of TBEA .