On June 26, Xuyi Ecological Environment Bureau of Huai'an City, Jiangsu Province issued a public announcement to approve the 100MW centralized photovoltaic power generation project in Maba Town, Xuyi County, Xuyi Changyao New Energy Technology Co., Ltd. The EIA information of the

project shows that the project is located in Gaoqiao Community, Yongxing Village and Baihe Village, Maba Town, Xuyi County, Huai'an City, Jiangsu Province, and the construction unit is Xuyi Changyao New Energy Technology Co., Ltd. The total investment of the project is 372.6 million yuan, the construction period is 9 months, the construction of centralized photovoltaic power generation project, the formation of upper power generation, the development of fisheries below.
The project plans to construct a centralized photovoltaic power generation project with a photovoltaic capacity of 100MW. The planned AC side capacity is about 100MW, the DC side capacity is 124.2592 MWp, and the AC side rated capacity is 99.84 MW.
The project is divided into 42 photovoltaic power generation units (15 3200 kVA units, 8 2560 kVA units, 13 2000 kVA units, 4 1600 kVA units and 2 1280 kVA units). A total of 725Wp high-efficiency monocrystalline silicon double-sided solar power generation module 171392 blocks are installed, and 312 320kw string inverters are selected. It is connected to the 110kV side of Maba Substation through a 110kV line, with a straight-line distance of about 4.1 km. The service life of
the project is 25 years, and the annual average power generation is 0.08 thousand kW · H/a 14692. After the completion of the project, the "full on-grid" power generation mode will be adopted.