China Electric Power Construction, announced on June 25 that on June 24, the company held a commencement ceremony for the 250 MW photovoltaic project of Sichuan Huadian Daocheng Lilang Phase I.

The project is located in Dengbo Township, Daocheng County, Ganzi Prefecture, Sichuan Province, with an altitude of 4500 to 4700 meters. The installed capacity of the first phase is 250 MW, and a new 220 kV booster station is built, which adopts the complementary mode of animal husbandry and light. On January 13
this year, the EPC project was tendered for general contracting. The tender announcement shows that the planned start date of the project is April 1, 2026, the planned full capacity grid-connected date is October 31, 2026, and the planned completion date is June 30, 2027.
Finally, Sinohydro Bureau 10 Co., Ltd. won the bid with a unit price of 3.071 yuan/W .