China Electric Power Construction Henan Engineering Co., Ltd., the opening ceremony of the 120 MW photovoltaic power generation project of Qingxiangshu (Phase II) in Shuangbai County, Datang County, Yunnan Province was held at 10 A. M. on September 27. The project has officially opened a new stage of comprehensive construction and full-speed construction.
China Electric Power Construction Henan Company said that due to multiple factors such as pre-formalities and site preparation, the project started four months behind the original plan.
Datang Group's e-commerce platform information shows that in March 2026, Datang Group launched the general contracting tender for the project, which was originally planned for the construction period from May 6 to November 30, 2026. Henan Engineering Co., Ltd. of China Electric Power Construction Group won the project with a total amount of 69505048.00 yuan .