On September 26, the online approval office of investment projects in Inner Mongolia issued a notice of change of projects, and Datang (Dalate Banner) New Energy Co., Ltd. declared the completion of the change of 1.5 million kilowatt photovoltaic sand control project in the second phase of Mengxi Tuoketuo.
The latest record information shows that the project adds new and supplementary explanations to the construction site and content of the project. According to
the latest information disclosed, the total investment of the second phase of the 1.5 million kilowatt photovoltaic sand control project from Tuoketuo to Mengxi is 845756.38 million yuan, and the construction site is located in Fengshuiliang Town, Bainijing Town and Jigestai Town, Dalate Banner, Ordos City, Inner Mongolia Autonomous Region. The construction period is December 2024 to December 2026. The total installed capacity of the
project is 1.5 million kilowatts, and six sub-projects are planned . Among them, Shuiquanwan Project is about 300MW, Yusuta Project is about 256MW, Shahaota Project is about 154MW, Shaoyingsha Project about 210MW, Hongnihao Project about 300MW and Hustai Project about 280MW.
According to the standard batch implementation and handover schedule, six sub-projects will be implemented in batches, stages and separately, and four 220kV booster stations and four 220kV collection lines, one 500kV collection station and one 500kV line (from the 500kV collection station of the project to the existing 500kV substation of Togtoh Power Company) will be constructed synchronously. The path length of 500kV line is about 7979, and supporting projects such as 30%? 4 H (450MW/1800MWh) energy storage device , maintenance road and ecological control are constructed.
According to the official website of Inner Mongolia Datang International Tuoketuo Power Generation Co., Ltd., a subsidiary of Datang Group, the evaluation opinions on the feasibility study report and investment application report of the second phase of 1.5 million kilowatt photovoltaic sand control project in Tuoketuo, Mengxi, were issued in May this year, marking that the project has entered a substantive stage of promotion.
It is reported that the second phase of the 1.5 million kilowatt photovoltaic sand control project in Mengxi Tuoketuo is a comprehensive project integrating photovoltaic power generation and Shago wasteland control, and has been included in the preparatory list of the third batch of national bases.