10 June, The National Energy Bidding Platform announced the successful candidates for the EPC project (Section 7, Section 8, Section 9, Section 10, Section 11 and Section 12) of Lingshao DC supporting Lingwu 2 million kilowatt composite photovoltaic base project of Ningxia Electric Power Guoneng Lingwu New Energy Co., Ltd.
The winning unit price is between 1.398 yuan/W and 1.504 yuan/W .
Among them, the lowest bidding unit price is 1.398 yuan/W , which is given by Hubei Electric Power Planning and Design Institute Co., Ltd .; The highest bidding unit price is 1.504 yuan/W , which is given by Jiangxi Electric Power Design Institute Co., Ltd. of China Power Construction Group.
The tender announcement shows that the total capacity of the tender is 1200 MW (DC side) , which is divided into six bidding sections . The capacity of each bid section is 200MW on the DC side and not less than 166.67 MW on the AC side .
It is reported that Guoneng Lingshao DC supporting Lingwu 2 million kilowatt composite photovoltaic base project started in July 2023, with a total investment of nearly 10 billion yuan , which is located in Baitugang Township, Lingwu City, Ningxia Hui Autonomous Region, with a gentle terrain. yuanyanghu Power Plant, Guoneng Ningdong Power Plant, Fangjiazhuang Power Plant and other large thermal power plants are distributed within 50 km of the surrounding area. It is about 35 km away from Lingshao DC ± 800kV Converter Station and about 60 km away from Qingshan 750kV Substation.