4 is 0! Jilin Announces Open Capacity of Distributed Photovoltaic Power Grid in the First Quarter of 2026

2025-12-29 16:32:06

Jilin Provincial Energy Bureau announced the accessible capacity of distributed photovoltaic in the first quarter of 2026 for reference by all parties to promote project planning and construction.

On December 29, the Energy Bureau of Jilin Province released the announcement of the open capacity table of the distributed photovoltaic power generation project in Jilin Province connected to the distribution network in the first quarter of 2026.

Publicity information shows that in the first quarter of 2026, the open capacity of four distribution networks in Jilin Province for distributed photovoltaic power generation projects is 0, the early warning level is red, and the early warning level of 31 places is yellow.

According to the requirements of the relevant documents of the State Energy Administration and in combination with the actual work, our Bureau organized the State Grid Jilin Electric Power Co., Ltd. and Jilin Local Electric Power Co., Ltd. to calculate the open capacity of distributed photovoltaic access to the distribution network in the first quarter of 2026. Local energy authorities, power grid enterprises and investors can work accordingly.

Attachment: Table

of Available Capacity of Distributed Photovoltaic Power Generation Project of Jilin Province Connected to Distribution Network in the First Quarter of 2026 Jilin Energy Bureau

December 29

, 2025
All can be viewed after purchase
Correlation

Jilin Provincial Energy Bureau announced the accessible capacity of distributed photovoltaic in the first quarter of 2026 for reference by all parties to promote project planning and construction.

2025-12-29 16:32:06

Hebei Province issued the Rules for the Implementation of the Development and Construction Management of Distributed Photovoltaic Power Generation (Draft for Opinions) to solicit opinions from the public, aiming at promoting the healthy and sustainable development of the distributed photovoltaic industry and building a new power system. The deadline for feedback is August 21, 2025.

2025-07-21 17:04:33

Jilin Province announced the open capacity of distributed photovoltaic access distribution network in the third quarter of 2025 for the reference of local energy departments, grid enterprises and investors.

2025-06-27 10:13:12

Since September 23, many places in Hebei, such as Shijiazhuang, Xingtai, Handan, Cangzhou, Hengshui and Baoding, have again notified an increase in cement prices by 30 yuan per ton.