Temporarily terminated! Xinjiang 1GW Photovoltaic Sand Control Project Bidding Major Change, the Official Has Cracked Down!

2025-09-02 17:01:10

On September 1, the announcement of temporary termination of the first, second, third, fourth and fifth bidding sections of the 1 million kilowatt photovoltaic sand control project in Shache County, Jinda Hongjing, Xinjiang Uygur Autonomous Region was issued. The announcement shows that, in view of the significant changes in the design schemes of the first, second, third, fourth and fifth bidding sections of the PC project in Jinda Hongjing Shache County, the original bidding documents can no longer meet the current project implementation needs, so it is decided to suspend the bidding activities of the PC project temporarily. After the adjustment and improvement of the project design scheme and the revision of the bidding documents, the bidding work of the project will be reorganized.

On September 1, the announcement of temporary termination of the first, second, third, fourth and fifth bidding sections of the 1 million kilowatt photovoltaic sand control project in Shache County, Jinda Hongjing, Xinjiang Uygur Autonomous Region was issued.

The announcement shows that in view of the major changes in the design schemes of the first, second, third, fourth and fifth bidding sections of the PC project of the 1 million kilowatt photovoltaic sand control project in Jinda Hongjing Shache County. The original bidding documents have been unable to meet the needs of the current project implementation, so it is decided to temporarily terminate the bidding activities of the PC project of the project. After the adjustment and improvement of the project design scheme and the revision of the bidding documents, the bidding work of the project will be reorganized.

Looking back on the previous bidding dynamics, on August 6, Jinda Hongjing Shache County's 1 million kilowatt photovoltaic sand control project PC project tender announcement was issued. The project is divided into five bidding sections, each with a scale of 200MW, and all bidding sections do not include exploration and design work.

The project plans to build a new photovoltaic power station of 1 million kilowatts, with an installed capacity of 1,000 MW on the AC side , using monocrystalline double-glass photovoltaic modules . Build a new 220KV step-up gathering station, 100MW * 2H capacity energy storage system and related ancillary auxiliary works. (For details, please refer to: Bidding for PC General Contracting of Xinjiang 1GW Photovoltaic Sand Control Project!

In addition, it is noteworthy that just two days before the announcement of the temporary termination of the project (August 29) . The Development and Reform Commission of Shache County, Xinjiang, issued a statement on the 1 million kilowatt photovoltaic sand control project in Jinda Hongjing Shache County. The

statement shows that the project is still in the preliminary stage of formalities, and the preliminary work of land use, planning and power grid access has not been completed . It has not yet met the legal conditions for bidding and construction.

After verification, some illegal elements have recently forged the signature of the Shache County Development and Reform Commission and forged the document "Opinions on the Power Supply Price of the 1 Million Kilowatt Photovoltaic Sand Control Project in Jinda Hongjing Shache County", which covers matters related to the price of power supply. In this regard, the Shache County Development and Reform Commission solemnly declared that the document was a forged official document, and the contents of the document were not true .

At the same time, the current content of "paying a deposit can undertake the 1 million kilowatt photovoltaic sand control project in Jinda Hongjing Shache County" is also false information . Any act of requiring payment of deposit, registration fee or other fees in the name of "government recommendation", "internal relations", "locking the project in advance" has nothing to do with the actual progress of the project, nor has it been approved by any government department in Shache County.

Xinjiang Shache County Development and Reform Commission said: "If the project enters the bidding stage, the bidding information will be released by the project investment enterprise Jinda Hongjing (Shache) New Energy Technology Co., Ltd. through the formal bidding platform in accordance with relevant laws and regulations.". Our committee will publicize the phased progress of the Pre-project formalities through official platforms such as the government's official website in due course.

The following is the original text of the statement:

All can be viewed after purchase
Correlation

On the evening of October 23, the board of directors of Xiuqiang Stock Announcement agreed to postpone the "Intelligent Glass Production Line Construction Project" and the "BIPV Glass and BIPV Component Production Line Project", and the time to reach the scheduled usable state was adjusted from December 31, 2025 to June 30, 2027, mainly due to macroeconomic and market environmental factors. As of September 30, 2025, the investment progress is lower than expected. This is the second extension of the "BIPV Glass and BIPV Component Production Line Project". On the same day, it announced the third quarterly report of 2025, with revenue increasing by 9.19% in the first three quarters, and net profit and other indicators declining.

2025-10-24 19:27:07

Xizang Changdu Basu County 450 MW Photovoltaic Project EPC General Contracting Pre-tender Tender Announcement

2025-10-24 10:08:03

Announcement of Bid Evaluation Results of Bid Section 1 of Urban Renewal Project in West Area of Tianjin West Railway Station (Beijing-Tianjin-Hebei Tongcheng Business District Phase I), Hongqiao District

2025-10-23 15:21:23

On October 22, the EPC general contracting of Yangdu 120MW Tea-Light Complementary Photovoltaic Power Generation Project in Huangshan District of China Electric Power Construction New Energy Company issued a public tender announcement. The tenderer is Huangshan Juyuan New Energy Co., Ltd.

2025-10-23 10:16:40

Tender Announcement for General Contracting (EPC) of 49 MW Roof Distributed Photovoltaic Project in Zhangwan District

2025-10-23 10:10:14

1.87 yuan/W, "Heluo Light" Phase III 80 MW Distributed Roof Photovoltaic Project Bid Results Released | Weekly Project Statistics (10.13-10.19)

2025-10-22 16:40:26

On October 22, the procurement project of photovoltaic modules (the first batch) for the 2025 distributed photovoltaic project of Henan Branch of Iron Tower Energy Co., Ltd. announced the results of winning the bid. Nanjing Oulu Electrical Appliances Co., Ltd., Yidao New Energy Co., Ltd. and Hengdian Group Dongci Co., Ltd. won the bid, ranking first to third.

2025-10-22 15:33:30

On October 20, the announcement of the failure of bidding for two photovoltaic power generation projects in Zhaotong City, Yunnan Province was issued. The projects involved are Tianba Photovoltaic Power Generation Project in Zhaoyang District and Banqing Photovoltaic Power Generation Project in Qiaojia County.

2025-10-22 15:09:42

On October 22, the tender announcement for the second batch of new energy photovoltaic power generation projects in Huize County, Qujing City, Yunnan Province in 2025 was issued. According to the announcement, the tender is divided into two bidding sections, with a planned investment of about 2.687 billion yuan and a bid bond of 200000 yuan.

2025-10-22 13:30:27

The meeting pointed out that the project has entered a critical construction period, with tight time and heavy tasks, requiring a 75-day on-site stationing to ensure that the target period of 860000 kilowatts grid-connected by the end of the year will be achieved.

2025-10-22 10:44:13

Longji Green Energy has won 400 MW offshore photovoltaic orders from Shanghai Electric Power, and BC technology has become the mainstream with high efficiency and reliability, marking the transformation of photovoltaic industry to "technology competition" and high-quality development.

2025-10-22 09:56:44

The deadline for submission of bidding documents and the time for bid opening are adjusted from 9:00 on October 21, 2025 to 9:00 on November 6, 2025.

2025-10-22 09:13:55

Recently, the Qingkong New Energy Military-Land Integration 500000 kW Photovoltaic EPC Project in Nilka County, Ili Prefecture, Xinjiang, issued a tender extension announcement again.

2025-10-21 17:01:16

The total investment of the project is 1.8 billion.

2025-10-21 14:27:25

On October 20, the Administrative Examination and Approval Service Bureau of Xinzhou City, Shanxi Province, issued the acceptance of environmental impact assessment documents for three construction projects, including the environmental impact report form for the photovoltaic power generation project (change) of the 100m W agricultural photovoltaic complementary energy storage system in yuanping City.

2025-10-21 14:24:03

On October 20, the announcement of the failure of bidding for two photovoltaic power generation projects in Zhaotong City, Yunnan Province was issued. The two photovoltaic projects involved are the Tianba Photovoltaic Power Generation Project in Zhaoyang District and the Banqing Photovoltaic Power Generation Project in Qiaojia County.

2025-10-21 13:51:07

From October 20 to 21, Datang Group successively released the announcement of the successful candidate for EPC general contracting of 60 MW photovoltaic power generation project in Menglinggou, yuanmou County and the announcement of the successful result of EPC general contracting of 80 MW photovoltaic power generation project in Moudingxu Street.

2025-10-21 13:22:57

On October 18, a foundation laying ceremony was held for the 100000 kilowatt photovoltaic power generation project (hereinafter referred to as "Jinchang Project") in Heqingtan, Yongchang County, Jinchang City, which was constructed by China Nuclear Huachen Southwest Branch.

2025-10-21 10:49:11

On October 20, the Guangdong Energy Bureau of the Guangdong Development and Reform Commission issued the Notice on Matters Relating to the Price Bidding of the New Energy Project Mechanism in 2025.

2025-10-21 10:05:37

Hunan deepens the market-oriented reform of new energy grid price, promotes the full entry of new energy into the market, establishes a differential settlement mechanism, implements step by step, incorporates bidding, guarantees reasonable income, and promotes the high-quality development of new energy.

2025-10-21 08:34:59

List of Proposed Photovoltaic Power Station Projects Last Week (10.13-10.19)

2025-10-20 20:40:32

On October 16, the opening ceremony of Guizhou Tongren Phoenix Airport Photovoltaic Project was successfully held.

2025-10-20 18:17:56

On October 17, the central enterprise China Coal Holdings announced the postponement of EPC bidding for five photovoltaic power generation projects on the same day, involving projects in Jiangxi, Jiangsu, Shanxi and other places.

2025-10-20 14:15:56

Digital New Energy DataBM. Com learned that on October 16, the EPC project of Xingtai Industrial and Commercial Distributed Photovoltaic Project of Huaneng Xiongan Green Energy Co., Ltd. of Huaneng Xiongan Energy Company issued a pre-tender announcement.

2025-10-20 09:18:25

On October 15, the 100000 kilowatt photovoltaic project of increasing production and expanding green in the oil and gas industry of Luntai County, Tarim Oilfield, Xinjiang, was officially started. According to the previous EPC tender announcement of the project, the total installed DC side capacity of the project is 120.5131 MWp and the AC side capacity is 100MW.

2025-10-18 11:00:00

On October 14, Ningxia Electric Power Guoneng Hongsibao New Energy Co., Ltd. "Ningxiang DC" supporting Hongsibao 1.5 million kilowatt new energy base project EPC project (seven tender sections, eight tender sections, nine tender sections) announced the successful candidates. China Construction Eighth Bureau General Contracting Construction Co., Ltd., China Railway Eleventh Bureau Group Co., Ltd. and China Electric Power Construction Group East China Survey and Design Institute Co., Ltd. are the first candidates for the three bidding sections respectively.

2025-10-17 14:50:48

Oil and gas industry in Luntai County, Tarim Oilfield, Xinjiang, has officially started the project of increasing production and expanding green by 100000 kilowatts.

2025-10-17 13:32:56

On October 15, Beijing Xinzhaoneng 450MW Distributed Photovoltaic Power Generation Project EPC General Contracting Project issued a tender announcement, the tenderer is Beijing Xinzhaoneng Energy Technology Co., Ltd.

2025-10-16 17:02:02

Digital New Energy DataBM. Com learned that on October 11, at the Gansu Characteristic Advantage Industry Docking Symposium held in Qingdao, two wind and solar projects were signed, involving a total installed capacity of 250 MW.

2025-10-16 16:59:25

Digital New Energy DataBM. Com learned that from September 29 to October 14, four distributed photovoltaic projects in Jiangxi and Guangdong issued termination announcements successively, involving a total installed capacity of about 222 MW.

2025-10-16 16:58:45

According to the Ministry of Energy and Water Resources of Tajikistan, on October 15, Chinese enterprises Wuhan Building Materials Industrial Design Research Institute Co., Ltd. and Yijing Optoelectronics signed cooperation agreements with the country respectively.

2025-10-16 16:56:26

On October 14, Ningxia Electric Power Guoneng Hongsibao New Energy Co., Ltd. "Ningxiang DC" supporting Hongsibao 1.5 million kilowatt new energy base project EPC project (seven, eight and nine bidding sections) public bidding candidates were announced. Six companies including China Construction Eighth Engineering Group Co., Ltd. were shortlisted for the three bidding sections, and China Construction Eighth Engineering Group Co., Ltd., China Railway 11th Engineering Group Co., Ltd. and East China Survey and Design Institute of China Power Construction Group were the first candidates for the three bidding sections respectively. The project was tendered on September 4, and the tenderer was Ningxia Electric Power New Energy Branch of the State Energy Group. The project is located in Hongsibao District, Wuzhong, Ningxia, covering an area of about 90,000 mu, including photovoltaic and wind power. The photovoltaic installed capacity in this tender is 479.68 MW.

2025-10-16 11:24:36

The announcement shows that the Three Gorges New Energy Power Generation (Longyou) Co., Ltd. intends to carry out the construction of the Three Gorges Energy Longyou Longyou and Fishery 50 MW Fishery Complementary Photovoltaic Power Generation Project in Baiban Village, Longzhou Street, Longyou County, covering an area of 5476 square meters (about 8.2 mu). A 110 kV booster station and its supporting facilities will be built in the project.

2025-10-16 09:40:50

On October 13, the People's Government of Changshan County, Quzhou City, Zhejiang Province issued the Announcement of Quzhou Ecological Environment Bureau on the Approval of the Environmental Impact Report Form of Changshan Xinchang 100MW Photovoltaic Power Generation Project of Zhejiang Changshan Huadian Fuxin Energy Co., Ltd. on October 13, 2025.

2025-10-16 09:40:07

On October 11, the People's Government of Jiaxian County, Yulin City, Shaanxi Province, issued a public announcement on the acceptance of environmental impact assessment documents for several projects, including the second phase of the photovoltaic multi-village power station in Qiancun, Jiaxian County, Jiaxian Agricultural and Rural Bureau.

2025-10-15 17:14:52

Digital New Energy DataBM. Com was informed that on October 14, Huadian Jinsha River Upstream Hydropower Development Co., Ltd. issued two tender announcements for EPC general contracting of photovoltaic power generation projects in counties with weak Xizang (Bangor 20 MW, Shuanghu 10 MW, such as 33 MW, Gongjue 14 MW).

2025-10-15 16:56:32

Recently, the pilot Qingkou Saltworks 250 MW fishing-photovoltaic complementary "photovoltaic composite" project officially started construction.

2025-10-15 16:52:32

On October 10, the Department of Ecology and Environment of Guangxi announced the acceptance of environmental assessment and approval of a batch of 500MW photovoltaic power generation projects of Beijing Energy Qinzhou Great Wall Million Kilowatt New Energy Demonstration Base Project (Phase II 850MW). The applicant is Qinzhou Jingneng Clean Energy Co., Ltd., a subsidiary of Beijing Energy Group.

2025-10-15 11:52:45

Among them, the photovoltaic clearing results are as follows: the scale of machine-made electricity is 3.6 billion kWh, a total of 31 projects, and the machine-made electricity price is 0.235 yuan/kWh;

2025-10-15 10:53:30

On October 10, the Department of Ecology and Environment of Guangxi announced the approval and acceptance of environmental impact assessment of two construction projects, including a batch of 500 MW photovoltaic power generation projects of Jingneng Qinzhou Great Wall Million Kilowatt New Energy Demonstration Base Project (Phase II 850MW), and the applicant was Qinzhou Jingneng Clean Energy Co., Ltd.

2025-10-14 17:34:27

The tender for the first bid section of the project issued a change announcement, and the scale and capital shrank.

2025-10-14 09:58:14

In the third quarter of 2025, the expansion of photovoltaic manufacturing capacity began to slow down. According to incomplete statistics from the Digital New Energy DataBM. Com, only 46 photovoltaic projects led by Chinese enterprises were dynamically updated from July to September.

2025-10-13 18:34:27

List of Proposed Photovoltaic Power Station Projects Last Week (10.06-10.12)

2025-10-13 17:20:25

The tender announcement shows that the six photovoltaic power station projects are located in Xinglonggong Village, Xinglonggong Town, Wen'an County, Langfang City, Hebei Province. Each project plans to build a photovoltaic power station with a DC side capacity of 7199.4kWp (an AC side capacity of 6000 kW), and the power generation mode is "full access to the grid".

2025-10-13 15:32:36

On October 9, China Coal Rongshui Rongshan Photovoltaic Project EPC General Contracting Project Tender Announcement was issued, and the tenderer was China Coal (Rongshui) New Energy Co., Ltd.

2025-10-13 15:31:37

On October 9, the Bureau of Ecology and Environment of Guigang City, Guangxi, issued a public announcement on the acceptance of environmental impact documents of the "Phase I Project of Xinhe Fishery and Light Integrated Photovoltaic Project in Gangnan District".

2025-10-13 15:29:44

The bidding announcement shows that the 300 MW photovoltaic project in Guyuan County has a total installed capacity of 300000 kilowatts, and the project category is photovoltaic power generation. The selected units selected through competitive allocation are investment enterprises.

2025-10-13 15:28:06

On October 11, the Henan Development and Reform Commission issued a public announcement on soliciting opinions on the Implementation Plan for Deepening the Market-oriented Reform of New Energy Grid Tariff in Henan Province (Draft for Opinions). The mechanism electricity price of stock projects is implemented according to the current benchmark price of coal-fired power generation in Henan Province (0.3779 yuan/degree). Incremental projects of general industrial and commercial distributed photovoltaic and large-scale industrial and commercial distributed photovoltaic projects are not included in the implementation scope of mechanism tariff. According to the principle of "monthly control proportion and annual control scale", a single project decomposes the mechanism electricity quantity and carries out price difference settlement.

2025-10-13 13:09:21

Construct centralized photovoltaic ground power station with AC side capacity of 9.8 MW.

2025-10-13 08:59:55

Recently, China Power Construction and China Nengjian, two major power central enterprises, have received huge orders of over 30 billion yuan from the Middle East, including 4G W photovoltaic projects. On the evening of October 10, China Energy Construction announced that its subsidiary consortium had signed three new energy general contracts in Saudi Arabia, amounting to about $2.745 billion (about 19.554 billion yuan), involving 3GW wind power and 2GW photovoltaic projects in Saudi Arabia, with a construction period of 26-30 months.

2025-10-12 11:00:00

From January to October, the forecast data of cement production in 31 provinces and cities in China showed the situation of cement production in various regions. From January to October, the total output of cement in China decreased compared with the same period last year, and the output in October also showed a downward trend compared with the same period last year, but increased compared with September. Among the provinces and cities, the cumulative output of Xizang from January to October increased by 13. 71% compared with the same period last year, while the cumulative output of Shanxi from January to October decreased by -16. 05%. On the whole, cement production in most provinces and cities has declined to varying degrees year on year.