On December 26, Lingyuan Sihedang 300MWp Centralized Parity Photovoltaic (EPC) Project announced that the tender was rejected because the number of valid bidders was less than statutory three. According to the tender announcement issued

on December 5, Lingyuan Sihedang 300MWp centralized parity photovoltaic (EPC) project invested 1.45 billion yuan , and the tenderer was Guozhong Great Wall (Tianjin) Asset Management Co., Ltd.
The project is located in Sihedang Town, Lingyuan City, Chaoyang City, Liaoning Province. The total installed capacity of the project is planned to be 300MWp and the total area of the site is about 5000 mu. A 220kV booster station is built in the middle of the photovoltaic site. The booster station covers an area of about 17.5 mu and is sent out by a 220kV line.
The project was originally scheduled to open on December 26.