On August 26, the Huaiji Branch of the Bureau of Ecology and Environment of Zhaoqing City, Guangdong Province, issued a public announcement on the acceptance of the EIA of the first phase of the 100m W Agricultural and Photovoltaic Complementary Project (re-approval) in Lengkeng Town, Huaiji County.
The EIA documents show that the project is a major change in the re-approval project, the construction unit is Huaiji County Huaijian New Energy Co., Ltd., the project is located in Lengkeng Town, Huaiji County, Zhaoqing City, Guangdong Province, Jiangshan Village, Tongguang Village, Furui Village, Loyalty Village, Hongcun Village, Longcun Village, Langzhao Village and the surrounding area of Tanfu Village. The construction of the booster station of this project has been partially completed. In the photovoltaic area, the installation of some components has been completed in some photovoltaic array areas.
The original project was approved on December 16, 2021, but in the later stage of the actual construction process, due to rent and other reasons, part of the land within the scope of the original project approval can not be used . If the installed capacity of 100MW is not reached, the construction unit shall select the land that meets the requirements in the nearby villages and towns to complete the remaining installed capacity of the project. After the re-approval of this
project, the floor area will be changed from 1.9434 million square meters to 1.7454 million square meters . 212,976 monocrystalline silicon PV modules are planned to be installed (201,366 are originally installed), with specifications and models of 545 Wp, 550 Wp and 585 Wp respectively. The planned construction capacity of the project is still 100MW . The actual total installed capacity is changed from 108.17 MWp to 120 MWp , and the total investment is still 375 million yuan .