On August 21, the tender announcement for the PC general contracting project of the 700000 kilowatt photovoltaic project of CGN Gaojingyuan Network Load Storage was issued, which was divided into two bidding sections . The tenderer is Qinghai Guangjing New Energy Co., Ltd., which is owned by China General Nuclear Power Group and Gaojing Solar Energy Co., Ltd .
The bidding content shows that the 700000 kilowatt photovoltaic project of Gaojingyuan Net-Charge Storage is located in Ledu District, Haidong City, Qinghai Province, with a planned installed capacity of 700MW . DC installed capacity 769.517 MWp . The project covers an area of 21,074 mu, which mainly belongs to natural grassland in the land category. The land is mainly located in Gaodian Town, Yurun Town and Dala Township. The planned construction period of the
project is September 27 , 2025, and all grid-connected power generation will be completed before May 30, 2026.
With regard to the principle of award, bidders must bid for two bid sections at the same time, and each bid section shall be evaluated separately, but a bidder can only win one bid section at most, and can not win both. The details are as follows:
With regard to the qualification of the bidder, in addition to having a good reputation and relevant qualifications, In terms of performance, it is necessary to provide the engineering performance of two or more similar projects in the past three years (before the deadline for bidding) (subject to the time of completion and acceptance) , and the single capacity of similar projects is greater than or equal to 100 MW . Consortium bidding is not accepted for
this project . The deadline for submission of
bidding documents/bid opening time is 9:00 on September 11, 2025.