On August 13, the announcement of public negotiation and procurement of photovoltaic module equipment procurement project of Qinyuan 100MW photovoltaic project of China Electric Power Construction Beijing Institute was issued, and the purchaser was Beijing Survey and Design Institute Co., Ltd. of China Electric Power Construction Group.
It is reported that China Power Construction Qinyuan 100MW Photovoltaic Project is located in the north of Qinyuan County, Changzhi City, Shanxi Province. The planned installed capacity of the project is 100MW , the DC side capacity is 119.67488MWp , the project is divided into 41 arrays, and a 220kV booster station is planned to be built. Connect to the 220kV bus of Jingneng Qinyuan Photovoltaic Booster Station, and the access mode is full access. The
content of the announcement shows that the scope of this procurement is the photovoltaic cell module equipment of Qinyuan 100MW photovoltaic project of China Electric Power Construction. This project designs and installs N-type 620Wp monocrystalline silicon double-sided solar cell modules with uniform color requirements, totaling 193,024 pieces. Capacity not less than 119. 67488 MWp.
According to the project requirements, the delivery
is planned to be completed on August 30, 2025, and the specific procurement scope is as follows:
It shall be a PV module R & D and manufacturing enterprise with independent legal personality, and shall have at least 600MW N-type monocrystalline silicon double-sided double-glass supply performance in the past three years (2022-2024) ; And provide at least one 200MW and above new energy project in the past three years (2022-2024) with the same equipment supply performance as this negotiation equipment. Consortium and agents are not accepted
in this procurement .
The bid closing/opening time is 15:00 on August 20, 2025.