On July 29, the photovoltaic area of the first phase of the Zero Carbon Industrial Park in Damao Banner, Baotou City, Inner Mongolia Autonomous Region officially started construction. The total investment of this
project is 900 million yuan, and the total construction capacity is 180 thousand kilowatts (180 MW) . Among them, wind power installed capacity is 120 thousand kilowatts (120 MW), photovoltaic installed capacity is 60 thousand kilowatts (60 MW) , and 25%/4 hours energy storage facilities are built synchronously.
It is reported that the project is located in Damao Banner, Baotou City, Inner Mongolia Autonomous Region. It is one of the second batch of green power supply projects in industrial parks in Inner Mongolia Autonomous Region. The main investors are Huadian Inner Mongolia Energy Co., Ltd. and Vision Science and Technology Group.
Previously, on March 18, 2025, Baotou City Damao Banner Zero Carbon Industrial Park Phase I Project (Photovoltaic Part) was accepted and announced. Baotou Huajing New Energy Co., Ltd. was responsible for the construction of this project, with a total investment of 357.36 million yuan .