On July 24, the tender announcement for EPC general contracting project of CGN New Energy Chongqing Chengkou 5 × 5.4MW Ground Distributed Photovoltaic Project was issued.
The announcement shows that the project is located in Chengkou County, Chongqing, and the tenderer is Zhongguang Nuclear New Energy Chongqing Co., Ltd ., which is a subsidiary of Zhongguang Nuclear Group.
This project is a CGN Chengkou 5 × 5.4MW photovoltaic project . They are CGN Chengkou Bashan Farmer 5.4MW Photovoltaic Project , CGN Chengkou Bashan Farmer Phase II 5.4MW Photovoltaic Project , CGN Chengkou Bashan Tianping 5.4MW Photovoltaic Project , CGN Chengkou Gaoyan Changtian 5.4MW Photovoltaic Project , CGN Chengkou Build Arashiyama 5.4MW Photovoltaic Project .
The project is planned to start on August 20 , 2025 and complete all grid-connected power generation by September 30 , 2025. In addition to requiring bidders to have good business reputation, business conditions and corresponding qualifications,
this tender requires bidders to have two or more similar construction and EPC project performance in the past three years (before the deadline for bidding) (whichever is the time of completion and acceptance). The single capacity of similar projects is greater than or equal to 20 MW. Consortium is not accepted
in this tender . The deadline for bid
opening/bidding is 9:00 on August 14, 2025.