Recently, the first phase of the project with a total investment of 200 million yuan and an annual output of 1.35 million tons of quartz sand for ultra-white photovoltaic glass has been successfully put into operation in Zhungeer Economic Development Zone. The completion of the project has successfully opened up the upstream and downstream industrial chain, laying a solid foundation for the development of the whole industry chain of photovoltaic panels and high-quality special glass in Zhungeer Economic Development Zone.
At present, after a period of trial production, Inner Mongolia Jingrui Quartz Sand Processing Co., Ltd. has formally put into operation the first phase of the project to achieve full-load production.
"Now six lines are in full load production, four washing lines and two rod grinding lines have been fully constructed and put into normal production to achieve full load operation." Zhao Jingshan, general manager of Inner Mongolia Jingrui Quartz Sand Processing Co., Ltd.
It is understood that the project is the upstream supporting project of the integrated project of comprehensive utilization of high-quality special glass of Inner Mongolia Yujing Science and Technology Co., Ltd. The high-quality silica quartz sand products produced by the project are mainly used in the midstream high-quality special glass and the second phase photovoltaic backplane project.
Zhao Jingshan introduced that Jingrui Quartz Sand Project currently produces 3000 tons of silica quartz sand per day, and the two high-quality special glass production lines of Yujing Science and Technology need 2040 tons of raw materials per day. After the project reaches production capacity, it can fully guarantee the raw material demand of the glass production line. At present, six production lines in the first phase of the project have achieved stable production, and four production lines in the second phase are planned to start construction next year to ensure the raw material demand of Yujing Phase II photovoltaic backplane project.
Inner Mongolia Yujing Technology Co., Ltd. settled in Zhungeer Economic Development Zone in November 2019, with a total investment of 14.3 billion yuan. It is planned to build a new, large-scale, high-tech, high value-added photovoltaic backplane, panel glass and high-quality special deep processing glass production line and a supporting deep processing production base in five to six years in four phases. At present, two photovoltaic backplanes and high-quality special deep processing glass production lines in the first phase of the project have been completed and put into operation, and the supporting upstream quartz sand processing production line for glass and downstream low-e energy-saving glass production line for deep processing have been completed and put into operation, with a total investment of 2.75 billion yuan. At the same time, the project of photovoltaic backplane glass deep processing production line with a total investment of 450 million yuan and an annual output of 40 million square meters is stepping up construction, and the main equipment of ultra-white calendered photovoltaic glass production line with an investment of 2.6 billion yuan has been ordered.