On January 20, Kubuqi Desert Base Ordos New Energy 1.7 million kilowatts Photovoltaic Project (Phase I Inner Mongolia Jingneng Zhunqi New Energy Co., Ltd. 600000 kilowatts) photovoltaic area EPC general contracting tender announcement was issued, and the tenderer was Inner Mongolia Jingtai Power Generation Co., Ltd. The project
is located in Zhungeer Banner, Ordos, with an installed capacity of 600MW (AC side) in the first phase and a new 220kV booster station. The Contractor shall be responsible for the whole process from the survey and design to the handover and production of the connecting part of the plot in the photovoltaic area. Bidders shall have good reputation and qualification. Since January 2023, there are at least three EPC general contracting performances of 200MWp and above centralized photovoltaic projects that have been put into operation. Consortium bidding is not accepted. The deadline for submission/bid opening is 9:00 on February 10, 2026.