Provincial Highway S282 (Jinshi Avenue)
: Reconstruction Project of Gaozhou Shigu-Jinshan Section of Provincial Highway S282 (Jinshi Avenue) is located in Shigu Town and Jinshan Street, Gaozhou City, Maoming City. The starting point K41 + 389 is located at the intersection of S282 and G207 in Shigu Town. The starting point of the route is laid out in the direction of Gaozhou City by using National Highway G207, and is routed to the southeast at Guluoshan Village. It passes through Dapoyuan, Baidiling, Heshan Village, Shentianpo and Pengshan, merges with Yongqing Avenue near Jiulong Lake, and then crosses with the north extension of Panzhou Avenue eastward. Then use the north extension line of Panzhou Avenue to connect with S282 southward to Wenlong Village, and the end pile number is K59 + 573.855. The total length of the project route is 18.222 km, which is composed of the new section of the realignment and the utilization section of the common line, of which the total length of the three common line sections is 7.902 km, and the total length of the new section is 10.320 km. According to the technical standard of two-way six-lane first-class highway, the design speed is 80km/H, the cement concrete pavement, and the standard width of the subgrade is 33.5m. There are 11 bridges (including ramp bridges), including 5 large bridges, 6 medium and small bridges, 33 culverts (including channel culverts), and 6 main route crossings (including 4 level crossings, 1 separated interchange, and 1 diamond interchange). Among them, the scope of the railway project: the main bridge of the new overpass project across the Yizhan Railway (left K56 + 225.8 ~ K56 + 345.8, right K56 + 155.8 ~ K56 + 275.8), the total length of the left and right is 240 m, the span arrangement is 2 × 60 m, and the full width of the bridge is 16.2 m.
Bidding content: all engineering contents included in the bidding documents, approved construction drawings and bill of quantities of the project, including the total length of the route of 18.222 km (including 10.320 km of new section and 7.902 km of common section), 11 bridges (including 5 large bridges and 6 medium and small bridges), There are 33 culverts, 6 main route crossings (4 level crossings, 1 separated interchange and 1 diamond interchange) and other key engineering contents.
Construction period (delivery date): 1,095 calendar days
Maximum bidding price limit: RMB 28,620 53059.
Bid winning information:
Bid winner: China Construction Eighth Engineering Division Co., Ltd. (Host)
Guangdong Sunny Highway Engineering Co., Ltd. (Member)
Bid price: 51674: RMB
0.44 million