On January 16, the tender announcement for general contracting of photovoltaic area construction of Luntai 500MW photovoltaic power generation project in Tarim Oilfield of Xinjiang was issued, and the tenderer was PetroChina Tower Oil (Luntai) New Energy Co., Ltd. The project
is located in Luntai County, Bazhou, Xinjiang, with 500 MW installed on AC side and 609.53 MW installed on DC side, supporting the construction of 220 kV booster station and 50 MW/100 MWh lithium iron phosphate energy storage system . .
The bidding scope covers the procurement, construction, commissioning, grid connection and warranty of materials supplied by the photovoltaic area B. It is planned to start construction on March 1, 2026 and connect to the grid with full capacity on April 30, 2027. The bidder shall have at least one photovoltaic EPC or PC performance of 100MW or above in the past three years, and the consortium bidding is not accepted. The bidding deadline and bid opening time are 8:00 on February 9, 2026.