On August 31, the centralized photovoltaic project in Lushan Street, Fuyang District, Hangzhou, Zhejiang, was officially started. The owner of the
project is Hangzhou Fuyang Yudean New Energy Co., Ltd., a subsidiary of Guangdong Energy Group, with a total installed capacity of 31.38 MW on the DC side and 31.15 MW on the AC side. Four sub-projects are implemented simultaneously (5.78 MW in Sanhe Village, 4.27 MW in Sanhe Village, 2.72 MW in Nanshan Village and 18.56 MW centralized photovoltaic project in Lushan Street Area).
Previously, on August 7, China Gezhouba Group First Engineering Co., Ltd., a subsidiary of China Nengjian, won the bid for EPC general contracting of the project with a quotation of about 65.909 million yuan and 2.12 yuan/W (AC side).
On August 19, Hengdian Dongci won the procurement bid of 31 MW photovoltaic modules at a unit price of 20.274 million yuan and 0.654 yuan/W.