On January 8, the 100MW Tea-Light Complementary Photovoltaic Power Generation EPC General Contracting Project in Pigeon Mountain Village, Honglin Town, Xuancheng City, Anhui Province was terminated due to insufficient valid bidders.
On January 9, the tenderee, Xuancheng Wanhong New Energy Co., Ltd., launched the second bidding. The project is located in Honglin Town, Xuanzhou District, with a planned capacity of 100MW, a DC side installed capacity of 125.MWp 09184, and an estimated contract price of 0.22 million yuan 35810. The construction period requires grid connection within 240 calendar days after the commencement order, and full capacity grid connection before the end of 2026. The bidder is required to have 70 MW and above PV EPC performance from 2022, and no more than 3 consortium bids are accepted. The bid closing/opening time is 10:00 on January 30, 2026.