On August 11, the change announcement of Mingte 700 MW Photovoltaic Power Generation Project (Phase I 300000 kW) in Fuping County, Baoding City, Hebei Province was issued. In the original bidding documents, "not accepting consortium bidding" is adjusted to "accepting consortium bidding", the time for obtaining bidding documents is extended to 17:00 on August 18, 2026, and the time for bidding and bid opening is extended from 9:30 on August 14, 2026 to 9:30 on September 1, 2026. The
EPC project has issued two tender announcements before, and was terminated less than a week after the first tender on May 18 due to the adjustment of the construction content, and the tender was restarted on July 24. They are the photovoltaic part with 300 MW (390 MWp on the DC side) and a new 220 kV booster station. It is planned to start construction on September 30, 2026 and realize full capacity grid-connected power generation on September 30, 2027.