3 August, The People's Government of Jiangyin City, Jiangsu Province issued a public announcement on the environmental impact report form of the fishing-photovoltaic complementary power generation project (re-approval) of Jiangyin Huangtuli Port, State Power Investment Corporation of Wuxi Xinggang New Energy Co., Ltd . The total investment of the
new project is 490 million yuan, with installed capacity of 153.1152 MWp on the DC side and 130 MW on the AC side. The scheme of block power generation and centralized grid connection is adopted.
Previously, on July 14, 2025, the project has obtained relevant approval and started construction in November 2025. Due to major changes in the location of land leasing in some photovoltaic areas under construction, it is now re-submitted for approval. It is planned to be completed in December 2026, with a total construction period of 12 months.