On July 9, China Nuclear Huineng Tongnan Xiaodu 100 MW Photovoltaic Power Generation Project invited public bidding for EPC general contracting, and the tenderer was Chongqing Tongnan Huitian New Energy Development Co., Ltd. The project
is located in many places in Tongnan District of Chongqing. It is planned to install about 100MW on the AC side and about 115.01MW on the DC side. A new 110kV booster station is connected to Tangba Substation. It is required to connect to the grid with full capacity within 121 days after the commencement order is issued. The bidder shall have one or more 100MW photovoltaic EPC performance since June 1, 2023, and accept the consortium bidding. The deadline for submission of bidding documents is 9:00 on July 30.