On February 27, China Energy Construction announced that it planned to raise no more than 9 billion yuan to invest in four new energy projects.
Zhongnengjian Hami "Solar (Thermal) Storage" Multi-energy Complementary Integrated Green Power Demonstration Project: with a total investment of 8.082 billion yuan and an installed capacity of 1,350MW. Solar thermal + photovoltaic integration project of
China Energy Engineering Group Zhejiang Thermal Power Construction Co., Ltd.: The total investment is 6.112 billion yuan, and the planned installed capacity is 1GW, including 900MW photovoltaic and 100MW solar thermal power generation and energy storage projects.
Hubei Yingcheng 300 MW Compressed Air Energy Storage Power Station Demonstration Project: With a total investment of 1.837 billion yuan, it is the world's first 300MW non-afterburning compressed air energy storage project, which uses salt cavern resources to store electricity at night and generate electricity during the day. Bash and Zankerdi Wind Power Project
in Uzbekistan: with a total investment of USD 997 million (equivalent to RMB 6.768 billion), it is located in Bukhara, Uzbekistan, with a total installed capacity of 1GW, including 158 wind turbines, two booster stations and two lines.