On June 12, Fujian Development and Reform Commission decided to abolish nine photovoltaic power station projects, such as Fuqing Tongwei Huijin Yuguang Integration (Phase II), due to the adjustment of factor guarantee policy and other factors. The grid connection and absorption resources are recovered by Fujian Electric Power Company of the State Grid, and the construction of projects that have been included in the annual development plan is required to be accelerated. Previously
, in February 2025, Fujian had abolished 10 projects totaling 1.143 million kilowatts for the same reason, with a cumulative scale of more than 2.1 million kilowatts.