On September 18, the Bureau of Economy and Information Technology of Chengdu City, Sichuan Province, launched the declaration of subsidies for the operation of energy storage projects in 2024. The operation subsidy of 0.3 yuan/kWh will be granted. The maximum annual subsidy for a single project with an installed capacity of less than 50,000 kW is 5 million yuan; the maximum annual subsidy for a single project with an installed capacity of 50,000 kW (inclusive) to less than 100,000 kW is 8 million yuan; and the maximum annual subsidy for a single project with an installed capacity of more than 100,000 kW (inclusive) is 10 million yuan.
The original text is as follows:
Notice
of Chengdu Economic and Information Bureau on the Declaration of Operation Subsidies for Energy Storage Projects in 2024 The competent energy departments of all districts (cities) and counties. State Grid Chengdu Power Supply Company and State Grid Tianfu New District Power Supply Company:
In order to further encourage and guide the development and application of energy storage, and help the peak, peak shaving and emergency reserve of the power system, According to the Notice of the General Office of Chengdu Municipal People's Government on Issuing the Action Plan for Optimizing Energy Structure and Promoting Urban Green and Low Carbon Development in Chengdu and the Policies and Measures for Optimizing Energy Structure and Promoting Urban Green and Low Carbon Development in Chengdu (CBF [2022] No.36), Notice of Chengdu Municipal Bureau of Economy and Information Technology and Chengdu Municipal Bureau of Finance on Printing and Issuing Detailed Rules for the Implementation of Policies and Measures for Optimizing Energy Structure and Promoting Urban Green and Low Carbon Development in Chengdu (Trial) (Chengjingxin Energy [2023] No.52) and other relevant requirements, the relevant matters concerning the declaration of operating subsidies for energy storage projects in Chengdu in 2024 are hereby notified as follows.
1. Application conditions
The energy storage system and auxiliary facilities shall have the functions of remote operation data transmission and remote control, and shall be connected to the new power load management system; the energy storage project shall comply with the relevant national specifications, standards and other provisions, and meet the relevant technical requirements for access to the power grid; The installed capacity of the declared project is not less than 100 kW , and the annual utilization hours after completion are not less than 600 hours . The independent energy storage project shall be executed according to the number of times of full charge and discharge not less than 250 times per year.
2. Support standards
for newly built energy storage projects (except pumped storage projects) put into operation since 2023, according to the actual annual discharge of energy storage facilities, give a subsidy of 0.3 yuan per kilowatt-hour , with an installed capacity of less than 50000 kilowatt s. The maximum annual subsidy for a single project is 5 million yuan ; the maximum annual subsidy for a single project with an installed capacity of 50,000 kilowatts (inclusive) to less than 100,000 kilowatts is 8 million yuan ; The installed capacity is more than 100000 kilowatts (including), and the maximum annual subsidy for a single project is 10 million yuan.
3. Application materials
(1) Chengdu Energy Storage Project Operation Subsidy Fund Application Form;
(2) Project application report;
(3) Project filing (approval or approval) documents, land formalities and other relevant materials;
(4) Business license, organization code certificate, tax registration certificate or multi-certificate business license (photocopy) and legal representative identity card (photocopy);
(5) Other financial support obtained or being declared for the project;
(6) Letter of commitment for the enterprise to declare in good faith;
(7) If the main body of the project investment filing is inconsistent with the main body of the project construction site, the relevant contract or lease agreement shall be provided.
4. Declaration procedures
(1) Enterprise declaration. The owner of the energy storage project (the main body of the record) prepares the relevant information according to the requirements, actively docks with the power supply company for verification, and logs on to the Chengdu "Tianfu Rong Yi Heng" platform (website https://tfryx.tfryb.com/) before October 15, 2025; Platform operation consultation telephone: 028-63911260), after obtaining the login identity, fill in and upload relevant project information and data as required. In order to facilitate the later statistics, all enterprises are requested to upload the editable Excel summary table (Annex 2) to the system synchronously when declaring, so that the local energy authorities can summarize it.
(2) First trial. The competent energy departments of all districts (cities) and counties, together with the local power supply companies, shall verify the authenticity of the declaration data and complete the online audit and submit it before October 30, 2025 (administrator login address https://10.1.80.112/zczd/gov/isvlogin; Platform operation consultation telephone: 028-63911260).
(3) Fund appropriation. The municipal Bureau of Economy and Information Technology shall organize the examination and verification of the declaration materials and allocate funds according to the procedures.
5. Requirements
for declaration (1) The subject of declaration shall be enterprises and relevant organizations operating in accordance with the law, without major accidents such as safety and environmental protection, within the validity period of the list of serious violations of law and dishonesty, and the projects involved shall comply with laws and regulations on safety, environmental protection, construction and fire protection.
(2) The competent energy departments of all districts (cities) and counties are requested to strengthen policy interpretation, actively organize qualified enterprises (institutions) to carry out the declaration work, and the project declaration materials are uniformly bound into a book in accordance with the requirements of the declaration, and the main body of the declaration is the main body of investment filing. If the same project conforms to the provisions of other similar subsidy policies at the municipal level and at all levels at the same time, it shall be supported in accordance with the principle of non-repetition and shall not be declared repeatedly.
(3) The competent energy departments of all districts (cities) and counties shall earnestly fulfill their responsibilities for the territorial management of the project, strictly check and verify the project declaration materials, organize the territorial power supply companies to conscientiously carry out the examination and verification of the project declaration materials, and be responsible for the authenticity of the declared projects and the project declaration materials; State Grid Chengdu Power Supply Company and State Grid Tianfu New Area Power Supply Company are responsible for organizing local power supply companies to verify the grid-connected time (since 2023), discharge hours and discharge data of new energy storage projects in 2024.
(4) After completing the online audit and submission, the competent energy departments of all districts (cities) and counties are requested to submit the project declaration materials (see Annex 1, one copy of paper materials, with electronic documents) and the project summary form (see Annex 2) to the Energy Planning and Management Office of the Municipal Bureau of Economy and Information Technology by October 30, 2025, which will not be accepted after the deadline. It must be consistent with the list and materials submitted for online review.
Chengdu Bureau
of Economy and Information Technology September 17
, 2025