On September 15, the tender announcement for the 1.6 million kilowatt photovoltaic power generation project (the second bid section) in Tori County, Tacheng Shangdian Power Co., Ltd. was issued. The project will build a 500000 kilowatt centralized photovoltaic power station , the scope of bidding includes equipment, roads and enclosures, excluding booster stations, etc. Bidders are required to have at least one new energy project construction performance since 2022, and do not accept consortium bidding. The deadline for bidding is 10:30 (Beijing time) on October 9, 2025. Previously
, on September 12, the tender announcement of the project (the first bid section) was issued, which will build a 550,000 kilowatt centralized photovoltaic power station. The scope of the tender includes equipment, fence and road works. The requirements for the qualification of bidders and the deadline for bidding are the same as those for the second bid section.