On September 1, the announcement of termination of bidding for photovoltaic modules for 120.28 MW supporting new energy EPC projects on some expressways in Anhui Province was issued. The reason for termination is that there are less than 3 bidders entering the second envelope quotation review. Earlier
, on August 8, the tender announcement for the project was issued, and the tenderer, Anhui Traffic Control Resources Co., Ltd., invited tenders for photovoltaic power station components and equipment for 120.28 MW supporting new energy EPC projects on some expressways in Anhui Province. The purchase quantity is about 169000 pieces. The estimated contract price is 85 million yuan, which was originally planned to be supplied within four months from August 2025. Nine photovoltaic enterprises ,
including Trina Solar, Dongfang Risheng and Xiexin Integration, participated in the first quotation.