On August 23, the 300 MW fishing-photovoltaic complementary photovoltaic power generation project in Tianquanhu Town, Xuyi County, Huai'an City, Jiangsu Province started. The
project covers an area of 6909 mu, with an installed capacity of 300 MW on the AC side, covering photovoltaic power stations, 220 kV booster stations, 30 MW/60 MWh energy storage systems and on-site transmission and transformation lines. The construction period is 9 months.
Previously, on April 22, 2025, TBEA announced that Xuyi Xinte Energy, its holding subsidiary, had invested 1.488 billion yuan in the construction of the project.