According to the announcement of Hongying Intelligence on December 4, The subsidiary of the company jointly won the bid of "Luopu 500000 kW/2 million kWh energy storage supporting 2 million kW photovoltaic power generation project (EPC general contracting) of Xinjiang Tongguang Science and Technology Co., Ltd." The project was terminated due to the announcement by the project bidding unit, Xinjiang Tongguang Science and Technology Co., Ltd., that the result of winning the bid was abolished. The reason for the abolition was a major policy adjustment. It is proposed to adjust the plan and then re-tender.
It is worth noting that the project has been changed for many times before. On July 8, 2024, the project was terminated for the first time due to the adjustment of bidding content. On July 21, the project was re-tendered, and four EPC bid sections were merged into one, and one supervision bid section was retained; On December 14, the consortium of six companies, including Hongying Intelligent Subsidiary, won the bid with 4.92 billion yuan, and now it has been abolished again one year later.
浙公网安备33010802003254号