27 November, Luhui Technology (Huaian) Co., Ltd. Lianshui Tangji 84.5MW Fishing-Photovoltaic Complementary Power Generation Project and Lianshui Huangying 45.5MW Fishing-Photovoltaic Complementary Power Generation Project EPC General Contracting Project were announced. The tenderer is Lvhui Technology (Huaian) Co., Ltd. For Tangji
Project, the installed capacity on the DC side is about 103.824 MWp, and the installed capacity on the AC side is about 84.5MW; for Huangying Project, the installed capacity on the DC side is about 57.5568 MWp, and the installed capacity on the AC side is about 45.5MW.
Both projects were connected to the grid with full capacity on November 30, 2026, with a construction period of 270 days. Bidders are required to have one EPC general contracting performance of centralized photovoltaic power generation of 100MW (including) or above (including 110kV and above booster stations) from January 1, 2022, and accept no more than two consortium bids. The deadline for bidding and bid opening is 15:00 on December 22, 2025.