On July 13, the EPC general contracting (the second batch) of the photovoltaic field construction project of the new energy base in the coal mining subsidence area of northern Shanxi started bidding. It is reported
that the project is located in Datong, Shanxi Province, with a total capacity of 1720MW. It is divided into three sections: 590 MW in the north of Xinrong, 550 MW in the east of Yungang and 580 MW in the left Yunnan. It is planned to start construction on August 20, 2025 and be completed on December 31, 2026. It is invested and constructed by Jinneng Holdings Jinbei Energy (Shanxi).
The bidder must have at least one photovoltaic EPC or construction performance of 100MW and above, and accumulative design performance of 500MW (including one single contract of more than 200MW). Consortium bidding is not accepted
in this tender, and one bidder can win one bid section at most. The deadline for
bidding is 10:00 on August 3, 2025.