On November 4, the successful candidate for the 500,000-kilowatt photovoltaic (EPC) project in Nilka County, Yili Prefecture, Xinjiang was announced. Changjiang
International Water Conservancy and Hydropower Engineering Construction Co., Ltd., Xingrun Construction Group Co., Ltd. and Hunan Xiangzhong Power Transmission and Transformation Construction Co., Ltd. were shortlisted, with a bidding unit price of 2.7 ~ 2.72 yuan/W, and Changjiang International ranked first with 2.7 yuan/W. Located in Nilka County, Ili, Xinjiang,
the project is a turnkey project with an investment of 1.8 billion yuan to build 500 MW photovoltaic and 125MW/500 MWh electrochemical energy storage facilities. It is planned to start on November 13, 2025 and complete on December 30, 2026, with a construction period of 413 days.