On November 4, Guoneng e-Recruitment released the announcement of successful candidates for EPC general contracting project of Ganluo Phase II Photovoltaic Power Generation Project of Dadu River Company. The project unit is Guoneng Dadu River New Energy Ganluo Co., Ltd. The project
is divided into three bidding packages, each with two enterprises shortlisted. For bid package 1 with a capacity of 83.7MW, China Construction Eighth Engineering Division General Contracting Construction Co., Ltd. is the first candidate with a 19519 of 0.72 million yuan, and the unit price is 2.332 yuan/W; for bid package 2 with a capacity of 165MW, Zhongnan Engineering Corporation of China Power Construction Group is the first candidate with a 25140 of 0.21 million yuan, and the unit price is 1.524 yuan/W; Bid package 3 has a capacity of 191.4MW, and Guiyang Power Construction Engineering Corporation of China ranks first with a 19899 of 0.16 million yuan and a unit price of 1.04 yuan/W. The AC side installed capacity of
the project is about 440MW. It is planned to start construction on October 15, 2025 and be connected to the grid for power generation before September 30, 2026, followed by a series of acceptance, transfer operation and completion acceptance arrangements.
浙公网安备33010802003254号