On November 4, the successful candidate for EPC general contracting of the photovoltaic area of Luntai 200MW photovoltaic power generation project in Tarim Oilfield, Xinjiang, was announced. China Construction Fourth Bureau Installation Engineering Co., Ltd., CNPC (Xinjiang) Petroleum Engineering Co., Ltd. and China Gezhouba Group Power Co., Ltd. were shortlisted, among which China Construction Fourth Bureau Installation Engineering Co., Ltd. ranked first with a bid price of 63.7355 million yuan (unit price 0.319 yuan/W). The AC side of the project
has an installed capacity of 200,000 kilowatts, supporting the construction of a 220 kilovolt booster station and a 20 megawatt/40 megawatt hour energy storage power station. . It is planned to start construction on November 20, 2025, complete the main body on June 30, 2026, meet the conditions for grid connection, connect to the grid on July 30, and connect to the grid with full capacity on October 30.