On November 3, the tender announcement for PC general contracting of photovoltaic power generation project of Shougang Group Mining Company was issued, and the tenderer was Huadian (Qian'an) New Energy Co., Ltd. The
project is located in Qian'an City, Tangshan City, Hebei Province, with a planned total installed capacity of 187.8 MW. The bidding scope covers the whole process from construction preparation to final acceptance at the expiration of the guarantee period.
The project is planned to start on December 1, 2025 (subject to the notice), be connected to the grid and put into operation on December 30, and be completed on June 30, 2026, with a construction period of 7 months. Consortium bidding is not accepted. Bidding documents can be obtained from 08:37 on November 3, 2025 to 17:00 on November 10, 2025. Bid closing/opening will be conducted at 09:00 on November 25.